An attempt to enable vSphere Fault Tolerance for a powered-on virtual machine fails. Which two scenarios would result in this failure? (Choose two.)___
A. The virtual machine has three vCPUs configured.
B. The host on which the virtual machine is running has insufficient memory resources.
C. The virtual machine has insufficient resources to accommodate full reservation plus the overhead memory.
D. VMware High Availability is enabled on the cluster of which this host is a member.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
相关试题
【多选题】
A vApp template recently added to a Content Library is not displayed. Which two actions could correct this problem? (Choose two.)___
A. Manually synchronize the library
B. Select the Download all library content immediately option
C. Select the Sync subscribed library option
D. Manually download the vApp template
【多选题】
What are three valid disk configurations for the vSphere Data Protection 6.x Appliance? (Choose three.)___
A. 500GB
B. 1TB
C. 1.5TB
D. 2TB
E. 4TB
【多选题】
Which three connection types are available when configuring a vSwitch in the vSphere Web Client? (Choose three.)___
A. VMkernel Network Adapter
B. Physical Network Adapter
C. Virtual Machine Port Group for a Standard Switch
D. vMotion Network Adapter
E. vSAN Network Adapter
【多选题】
Which three features can be enabled for a new host cluster? (Choose three.)___
A. Storage Distributed Resource Scheduling
B. High Availability
C. Fault Tolerance
D. Distributed Resource Scheduling
E. Virtual SAN
【多选题】
An administrator receives a report that no real time statistics are available for a virtual machine in the vCenter Server inventory. Which two statements indicate likely causes of the problem? (Choose two.)___
A. The virtual machine is powered off.
B. The host containing the virtual machine is disconnected from vCenter Server.
C. There is insufficient real time data to display the information.
D. The vCenter Server service is not running.
【多选题】
Your manager has given you a bash script that retrieves data for ESXi 6.x host configurations. This data needs to be collected right after the installation of a host and must be run directly on the host. Which two actions can be used to run this script on an ESXi host? (Choose two.)___
A. Connect to the host with Ruby vSphere Console and run the script from there.
B. Enable SSH access from the Direct Console User Interface.
C. Enable the ESXi Shell from the
D. irect Console User Interface.
【多选题】
Which two are true about the Risk badge in vRealize Operations? (Choose two.)___
A. The Risk badge indicates potential future problems that may degrade the performance of the system.
B. Risks may require attention in the near future.
C. The Risk badge indicates problems that are degrading performance of the system.
D. Risks require attention now to correct system performance problems.
【多选题】
vSphere Update Manager allows which two virtual machine attributes to be upgraded? (Choose two.)___
A. Virtual machine firewall policies for NSX.
B. Software Packages in the virtual machine.
C. Virtual machine Hardware Version.
D. VMware Tools Upgrade.
【多选题】
What are two benefits of using NFS 4.1 with vSphere 6.x as compared to NFS 3? (Choose two.)___
A. NFS 4.1 supports Kerberos Authentication
B. NFS 4.1 supports multipathing
C. NFS 4.1 supports IPv6
D. NFS 4.1 supports hardware acceleration
【多选题】
Which three statements are true regarding Fault Tolerance? (Choose three.)___
A. Applications need to be continuously available to users.
B. Applications without native clustering capabilities can be protected.
C. Custom clustering solutions are complicated to configure and maintain.
D. Applications that have 16 vCPUs are supported.
E. Prevents application crashes by analyzing the workload and correcting problems.
【多选题】
Which two statements are true regarding VMware vSphere Flash Read Cache (vFRC)? (Choose two.)___
A. Cache fills and cache evictions happen in the granularity of a cache block size.
B. vFRC caches data from both read and write I/Os, but write I/Os are always serviced by the underlying storage.
C. vFRC caches data from both read and write I/Os, but write I/Os are always serviced by the underlying cache data.
D. Cache fills and cache evictions happen in the granularity of the disk block size.
【多选题】
What are two possible causes of Storage Distributed Resource Scheduler (SDRS) being disabled on one or more virtual machine disks in a datastore cluster? (Choose two.)___
A. The virtual machine has vSphere Fault Tolerance disabled.
B. The virtual machine is a template.
C. The virtual machine swap file is on a shared datastore.
D. The disk is a CD-ROM/ISO file.
【多选题】
An administrator attempts to install vCenter Single Sign-On Server. The installer returns an error message indicating that the installation failed. Prior to the installation, all setup prerequisites were met. The administrator has generated a vCenter Server Single Sign-On support bundle. Which two files should the administrator analyze to determine the cause of the failure? (Choose two.)___
A. Server\utils\logs\imsTrace.log
B. Server\utils\logs\install.txt
C. %TEMP%\utils\logs\vminst.log
D. %TEMP%\vminst.log
【多选题】
An administrator is unable to remove an ESXi 6.x host from a vSphere Distributed Switch. What are two likely reasons for this issue? (Choose two.)___
A. Vmkernel interfaces on the switch are still in use.
B. VM Network port group adapters are connected to different switch.
C. Physical NICs are migrated to different switch.
D. VM Network adapters are connected to this switch.
【多选题】
Which two Identity Sources are available to add for vCenter Single Sign-On authentication? (Choose two.)___
A. LocalOS
B. OpenLDAP
C. NIS as an LDAP Server
D. VCMSDS
【多选题】
What are three goals of resource management within a cluster? (Choose three.)___
A. To prevent virtual machines from monopolizing resources and to guarantee predictable service rates.
B. To exploit undercommitted resources and overcommit with graceful degradation.
C. To provide solutions to potential problems that you might encounter when using vCenter Server.
D. To control the relative importance of virtual machines and provide flexible dynamic partitioning.
E. To provide additional network administration capabilities.
【多选题】
Which three actions can be taken as a result of executing the vSphere Update Manager 6.x scan and remediation wizards? (Choose three.)___
A. Install and upgrade software in virtual machines.
B. Upgrade the firmware on ESXi host devices.
C. Upgrade and Patch ESXi hosts.
D. Install and update third-party software on hosts.
E. Upgrade virtual machine hardware.
【多选题】
Which two statements are true about deploying and using vSphere Replication? (Choose two.)___
A. ESXi hosts managed by a single vCenter Server instance require a connection between the two vSphere Replication appliances.
B. Sites managed by different vCenter Server instances require a connection between the two vSphere Replication appliances.
C. Sites managed by different vCenter Server instances require the use of Site Recovery Manager and a connection between the two vSphere Replication appliances.
D. ESXi hosts managed by a single vCenter Server instance require a single vSphere Replication appliance.
【多选题】
An administrator is attempting to power on a virtual machine, but the task is hanging at 95%. What three scenarios best explain why this problem is happening? (Choose three.)___
A. A virtual machine question is currently being posed to the administrator.
B. Another task for the virtual machine or other component is already in progress.
C. The VMware High Availability cluster has insufficient resources to guarantee failover.
D. The host has lost access to the storage device containing the virtual machine files.
E. The host is under resource contention and unable to power on the virtual machine.
【多选题】
Which three features are not supported when using Fault Tolerance in vSphere 6.x? (Choose three.)___
A. Virtual Volumes (VVOLS)
B. Storage vMotion
C. Virtual Machine Component Protection
D. vMotion
E. vSphere Distributed Switches
【多选题】
Which two storage controller configurations can be used with Virtual SAN? (Choose two.)___
A. SAS controllers in Passthrough mode
B. SAS controllers in RAID0 mode
C. SAS controllers in RAID1 mode
D. SAS controllers in RAID10 mode
【多选题】
Which three are requirements when using vMotion to move a virtual machine across vCenter Server systems? (Choose three.)___
A. Both vCenter Servers must be using Enhanced Linked Mode.
B. Both vCenter Servers must be in the same Single Sign-On Domain.
C. Time must be synchronized.
D. Duplicate VM MAC addresses must be configured.
E. Both vCenter Servers must have High Availability enabled on source and destination clusters.
【多选题】
Which two components can be used when configuring Enhanced Linked Mode? (Choose two.)___
A. vCenter Server Appliance
B. vRealize Operations Manager
C. vSphere Management Appliance
D. vCenter Server for Windows
【多选题】
An organization has a number of virtual machines that would benefit from Fault Tolerance. These include: <A single vCPU Apache Server> < A dual vCPU vCenter Server> < A quad vCPU SQL Server> <An eight vCPU Hadoop Server>. Which two virtual machines can be configured to use VMware Fault Tolerance? (Choose two.)___
A. Apache Server
B. vCenter Server
C. SQL Server
D. Hadoop Server
【多选题】
Which two badges are major badges in vRealize Operations? (Choose two.)___
A. Risk
B. Efficency
C. Workload
D. Faults
【多选题】
An administrator is deploying multiple Windows 2003 Virtual Machines from the same template. What two steps should be taken to avoid network conflicts? (Choose two.)___
A. Customize the guest operating system.
B. Install VMware Tools into the new virtual machines.
C. Copy the Microsoft Sysprep tools onto the vCenter Server system.
D. Ensure the e1000 vmnic is selected for each new virtual machine.
【多选题】
Which three conditions would prevent Storage I/O Control from being enabled on a group of datastores? (Choose three.)___
A. The datastores planned for the solution are used by different vSphere clusters.
B. A datastore planned for the solution is configured as a Raw Device Mapping file.
C. A datastore planned for the solution has three extents.
D. A datastore planned for the solution is configured as NFS.
E. The organization has an Enterprise license.
【多选题】
Which two actions are prerequisites to adding ESXi 6.x hosts to a vSphere Distributed Switch? (Choose two.)___
A. Verify that there is at least one Distributed Port Group on the Distributed Switch.
B. Verify that the Distributed Port Group have active uplinks configured in its teaming and failover policy.
C. Verify that the
D. istributed Switch has been configured with a Network Profile.
【多选题】
An organization has configured Distributed Power Management (DPM) on a vSphere 6 cluster. The organization wants to be alerted when an ESXi host has been powered down by DPM. Which two options represent the type and name of the alarm that would accomplish this? (Choose two.)___
A. DrsEnteringStandbyModeEvent
B. DrsEnteredStandbyModeEvent
C. Event-based
D. Condition-based
【多选题】
Which two allow for the disabling of Network Rollback operations? (Choose two.)___
A. Modifying the vpxd advanded configuration options and adding the config.vpxd.network.rollback key
B. Modifying the C:\ProgramData\VMware\CIS\cfg\vmware-vpx\vpxd.cfg file and adjusting the<rollback> xml tag
C. Modifying the C:\ProgramData\VMware\CIS\cfg\vmware-vpx\vpxd.cfg file and adjusting the <networkrollback> xml tag
D. Modifying the C:\ProgramData\VMware\CIS\cfg\vmware-vpx\firstboot\vpxd-service- spec.prop file and adjusting the <rollback> xml tag
【多选题】
An administrator is tasked with performing a vMotion migration of a virtual machine. The virtual machine is configured as follows: <vSphere Flash Read Cache (vFRC) enabled> <Is part of a Distributed Resource Cluster (DRS) Cluster> Which two statements are true? (Choose two.)___
A. Each ESXi host in the cluster supports multiple virtual flash resources.
B. Each ESXi host in the cluster supports one virtual flash resource.
C. DRS treats powered-on virtual machines with Flash Read Cache as having a preferred affinity to their current host and moves them only for mandatory reasons.
D. DRS treats powered-on virtual machines with Flash Read Cache as having a required affinity to their current host and does not move them.
【多选题】
An administrator is using the Host Failures to Tolerate Admission Control Policy for a vSphere High Availability ___ cluster. When configuring this setting on the cluster, the administrator sees this error message: <Insufficient resources to satisfy HA failover level on cluster > What are two likely causes for the error? (Choose two.)(AB)
A. The hosts in the cluster are disconnected.
B. A host in the cluster is displaying an HA error.
C.
D. istributed Resource Scheduler has not been configured on the cluster.
【多选题】
What are two ways to identify TCP/IP stack information? (Choose two.)___
A. Using the vSphere Web Client
B. Using esxcli network ip netstack
C. Using esxcfg-netstack
D. Using the vSphere Client
【多选题】
Which two actions are required when enabling vFlash Read Cache for a virtual machine's virtual disk? (Choose two.)___
A. A value in the Virtual Flash Read Cache text box must be entered.
B. A Flash Resource Pool for Cache size reservation must be entered.
C. The Device backing and the block size must be configured.
D. The
E. nable virtual flash host swap cache check box must be selected.
【多选题】
What two IT infrastructure components are virtualized by vSphere Essentials? (Choose two.)___
A. Networks
B. Applications
C. Storage
D. Management
【多选题】
When attempting to access a virtual machine, an administrator is unable to login using the vSphere credentials. What two options are probable causes of the authentication failure? (Choose two.)___
A. The vSphere credentials have not been granted permissions.
B. The vSphere credentials are granted read-only permissions.
C. The vSphere credentials are granted no-access permissions.
D. The vSphere credentials are not a member of the local administrator group.
【多选题】
An administrator is performing a scripted installation of ESXi 6.x. In which three locations does the script need to be? (Choose three.)___
A. PXE Server
B. HTTPS
C. FTP
D. NFS
E. VVOLs Datastore
【多选题】
In order for a company to meet regulatory requirements, all ESXi 6.x Hosts must be configured to direct logs to a syslog server. What are two ways ESXi hosts can configured for this action? (Choose two)___
A. Use the esxcli system syslog command.
B. Edit them in the ESXi host Advanced System Settings.
C. From the Syslog collector user interface of the Web Client.
D. Syslog logging is not available for
E. SXi Hosts.
【多选题】
Which three actions can be executed when an alarm is triggered? (Choose three.)___
A. Send an email.
B. Send an SNMP trap.
C. Run a script or command.
D. Run an Orchestrator workflow.
E. Send a trigger to syslog.
【多选题】
An administrator is attempting to power on a virtual machine, but is unable to do so. Which two reasons are probable causes of the failure? (Choose two.)___
A. Storage access to the virtual machine swap file has been lost.
B. One of the virtual machine VMDK files is locked.
C. Virtual machine is running CentOS 7.0 64-bit.
D. Virtual machine has Hyper-Threading enabled.
推荐试题
【多选题】
全体员工应自觉做到“___”四不伤害。
A. 他人保护我不受伤害
B. 不伤害自己
C. 不伤害他人
D. 不被他人伤害
E. 我保护他人不受伤害
【多选题】
全体员工应自觉做到“___”四不伤害。
A. 他人保护我不受伤害
B. 不伤害自己
C. 不伤害他人
D. 不被他人伤害
E. 我保护他人不受伤害
【多选题】
犬咬伤的现场急救要点是___。
A. 不要惊慌奔跑饮酒,以免加速蛇毒在人体内扩散
B. 咬伤后应立即用浓肥皂水或清水冲洗伤口至少15min,同时用挤压法自上而下将残留伤口内唾液挤出,然后再用碘酒涂搽伤口
C. 少量出血时,不要急于止血,也不要包扎或缝合伤口
D. 尽量设法查明该犬是否为“疯狗”,对医院制订治疗计划有较大帮助
E. 已昏迷病员应保持气道通畅,有条件时给予氧气吸入。呼吸心跳停止者,按心肺复苏法抢救,并联系医院救治
【多选题】
若需变更工作班成员时,应满足___条件,新工作人员才可进行工作?
A. 完成对新工作人员进行安全交底手续后
B. 经工作票签发人同意
C. 经工作许可人同意
D. 经工作负责人同意
E. 经专责监护人同意
【多选题】
设备停电检修,在可能来电侧的断路器(开关)、隔离开关(刀闸)上,下列哪些措施,必须执行___?
A. 隔离开关(刀闸)操作把手应锁住
B. 断开保护出口压板
C. 断开控制电源
D. 断开合闸电源
【多选题】
生产安全事故的应急救援体系是保证生产安全事故应急救援工作顺利实施的组织保障,主要包括___。
A. 应急救援指挥系统
B. 应急救援日常值班系统
C. 应急救援信息系统
D. 应急救援技术支持系统
E. 应急救援组织及经费保障
【多选题】
生产班组负责生产作业风险控制的执行,做好___等风险管控
A. 人员安排
B. 任务分配
C. 资源配置
D. 安全交底
E. 工作组织
【多选题】
施工设备属于下列哪些情况,才允许在几个电气连接部分使用一张工作票:___
A. 属于同一电压
B. 几处工作共用一套测试仪器
C. 没有可能触及带电导体的几个电气连接部分
D. 同时停送电
E. 位于同一平面场所
【多选题】
手持电动工具下列哪些情况下不能使用___。
A. 绝缘损坏
B. 有外壳保护
C. 保护线脱落
D. 插头插座开裂
【多选题】
同时符合___条件,可以使用一张带电作业工作票。
A. 同一类型的带电作业工作
B. 同一部门
C. 在同一变电站内
D. 依次进行的工作
【多选题】
外来施工单位进入变电站工作,设备运行管理单位签发人对 ___、工作票上所填安全措施是否正确完备负责。
A. 工作班成员是否恰当和充足
B. 工作负责人是否恰当和充足
C. 工作必要性
D. 工作安全性
【多选题】
下列哪些措施是低压回路停电的安全措施?___
A. 将检修设备的各方面电源断开取下可熔保险器
B. 在开关或刀闸的操作把手上挂“禁止合闸,有人工作!”的标识牌
C. 工作前必须验电
D. 根据需要采取其他安全措施
【多选题】
有害气体中毒开始时有流泪、眼痛、呛咳、咽部干燥等症状,应引起警惕。稍重时会___。
A. 头痛
B. 气促
C. 胸闷
D. 眩晕
E. 惊厥昏迷
【多选题】
在日常工作中要贯彻预防为主原则,通过实施安全风险管理体系,开展___,落实事故预防措施,使管理对象始终保持在安全状态,防止风险失控。
A. 风险预防
B. 风险辨识
C. 风险评估
D. 风险分析
E. 风险控制
【多选题】
在生产活动所涉及的场所、设备(设施)、运行操作、检修施工等特定区域以及其它有必要提醒注意危险和有害因素的地点,按照标准要求,设置清晰醒目、规范统一的___等各类安全设施,并规范使用。
A. 安全围栏
B. 标识标志
C. 报警装置
D. 防坠装置
E. 安全措施
【多选题】
浙江省电力公司安全文化建设方向,就是以人为本,建设安全___,将安全理念扎根于员工的心灵深处,升华为员工的自觉行动,建设浙江公司更加美好的家园,成就浙江电力更加辉煌的事业。
A. 理念文化
B. 行为文化
C. 制度文化
D. 环境文化
E. 物质文化
【多选题】
浙江省电力公司安全文化建设方向,就是以人为本,建设安全___,将安全理念扎根于员工的心灵深处,升华为员工的自觉行动,建设浙江公司更加美好的家园,成就浙江电力更加辉煌的事业。
A. 理念文化
B. 行为文化
C. 制度文化
D. 环境文化
E. 物质文化
【多选题】
50专责监护人临时离开现场时,应该___
A. 指定能胜任的人临时代替
B. 通知被监护人员停止工作
C. 通知被监护人员离开工作现场
D. 特别告知被监护人员安全注意事项
【单选题】
个人贷款,是指贷款人向符合条件的自然人发放的用于个人消费、___等用途的本外币贷款。
A. 生产经营
B. 房产按揭
C. 股市投资
D. 固定资产
【单选题】
贷款人应根据审慎性原则,完善授权管理制度,规范审批操作流程,明确贷款审批权限,实行___和授权审批,确保贷款审批人员按照授权独立审批贷款。
A. 逐级审批
B. 审贷合并
C. 审贷分离
D. 一审终审
【单选题】
贷款人应要求借款人___签订借款合同及其他相关文件,但电子银行渠道办理的贷款除外。
A. 放贷后
B. 当面
C. 审查时
D. 受理时
【单选题】
采用贷款人受托支付的,贷款人应要求借款人在使用贷款时提出___,并授权贷款人按合同约定方式支付贷款资金。
A. 支付申请
B. 交易合同
C. 交易对手身份信息
D. 交易对手账号
【单选题】
一年以内(含)的个人贷款,展期期限累计不得超过___;一年以上的个人贷款,展期期限累计与原贷款期限相加,不得超过该贷款品种规定的最长贷款期限。
A. 1年
B. 该贷款品种规定的最长贷款期限
C. 2年
D. 原贷款期限
【单选题】
个人贷款调查应以___,采取现场核实、电话查问以及信息咨询等途径和方法。
A. 现场调查为主、非现场调查为辅
B. 实地调查为主、间接调查为辅
C. 双人调查为主、单人调查为辅
D. 面谈调查为主、非面谈调查为辅
【单选题】
固定资产贷款,是指贷款人向___或国家规定可以作为借款人的其他组织发放的,用于借款人固定资产投资的本外币贷款。
A. 个人
B. 企(事)业法人
C. 国家机关
D. 房地产开发企业
【单选题】
固定资产贷款中,贷款人应在合同中与借款人约定对借款人相关账户实施___,必要时可约定专门的贷款发放账户和还款准备金账户。
【单选题】
固定资产贷款发放和支付过程中,贷款人应确认与拟发放贷款同比例的项目___足额到位,并与贷款配套使用。
A. 施工人员
B. 管理人员
C. 担保
D. 资本金
【单选题】
固定资产贷款中,单笔金额超过项目总投资()或超过___人民币的贷款资金支付,应采用贷款人受托支付方式。
A. 10%,1000万
B. 5%,500万元
C. 5%,1000万
D. 10%,500万
【单选题】
贷款人从事项目融资业务,应当以___为核心,重点从项目技术可行性、财务可行性和还款来源可靠性等方面评估项目风险,充分考虑政策变化、市场波动等不确定因素对项目的影响,审慎预测项目的未来收益和现金流。
A. 偿债能力分析
B. 用途分析
C. 还款周期分析
D. 担保分析
【单选题】
贷款人应当根据项目预测现金流和___等因素,合理确定贷款期限和还款计划。
A. 财务可行性
B. 投资回收期
C. 政策变化
D. 政策
【单选题】
贷款人应当与借款人约定专门的___,并要求所有项目收入进入约定账户,并按照事先约定的条件和方式对外支付。
A. 支付方式
B. 项目收入账户
C. 贷款管理人员
D. 项目管理人
【单选题】
省联社决定利用___年左右时间,在全省农信社开展信贷资产质量集中攻坚。
【单选题】
省联社围绕全面提升信贷资产质量总目标,坚持问题导向,聚焦信贷经营管理薄弱环节,全面推进___,开展信贷重点领域风险专项整治,推进建设()。
A. 合规放贷、信贷文化
B. 合规放贷、合规文化
C. 从严治贷、合规文化
D. 从严治贷、信贷文化
【单选题】
2021年末全省农信社不良贷款占比整体控制在___以内。
【单选题】
新增贷款重点投向“三农”、脱贫攻坚、___领域。
A. 民营和小微企业
B. 大型企业
C. 中型企业
D. 中大型企业
【单选题】
新增贷款重点关注___,做到实质不合规的贷款坚决不放,没有把握收回的贷款坚决不放。
A. 借款人主体资格
B. 担保人主体资格
C. 第一还款来源
D. 第二还款来源
【单选题】
问题大查摆中,信贷从业人员要结合自身岗位查摆制度执行不到位、___等问题
A. 落实监管要求不到位
B. 职责落实不到位
C. 信贷管理漏洞与缺位
D. 信贷质量管控不到位
【单选题】
关联贷款中,对于实际用款人积极配合的,追加___有效资产作为贷款抵质押担保,并按照集中度监管规定,制定贷款逐步压降计划。
A. 名义用款人
B. 第三人
C. 实际用款人
D. 名义用款人和实际用款人
【单选题】
虚假贷款能够还原借款主体的,按照___进行整改;
A. 还原主体
B. 逐步压缩
C. 法律途径
D. 协商
【单选题】
对于房地产行业贷款,已经超过监管规定的行社___发放新增房地产行业贷款,并逐步压降存量余额达到监管规定。
A. 不得
B. 备案通过后
C. 可以
D. 按5%的增幅