刷题
导入试题
【单选题】
An administrator has a virtual machine that requires four times the compute resources than other virtual machines on the same ESXi 6.x host. How should the administrator configure the virtual machine settings, in order to be prepared for any resource contention? ___
A. Set the shares of the priority virtual machine to High and the rest to Low.
B. Set the shares of the priority virtual machine to High.
C. Set the shares of the priority virtual machine to High and the rest to Normal.
D. Set the shares of the priority virtual machine to Normal and the rest to Low.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
答案
A
解析
暂无解析
相关试题
【单选题】
Which type of Adapter does not require vmkernel networking? ___
A. Independent Hardware iSCSI Adapter
B. Dependent Hardware iSCSI Adapter
C. Software iSCSI Adapter
D. Software FCoE Adapter
【单选题】
During the installation of ESXi 6.0, the following error message is reported: Hardware Virtualization is not a feature of the CPU, or is not enabled in the BIOS. Which condition would generate this message? ___
A. LAHF/SAHF is not enabled in the BIOS.
B. NX/XD is not enabled in the BIOS.
C. SSE3 is not enabled in the BIOS.
D. Hyperthreading is not enabled in the BIOS.
【单选题】
An administrator is unable to login to vCenter Server when using the vSphere web client. The administrator successfully accessed vCenter Server using the client earlier the same day. What is the most appropriate first step the administrator should take to resolve this issue? ___
A. Verify the web browser being used has Adobe Flash plugin version 11.5 or later
B. Verify the vCenter Single Sign-On service is running on the vCenter Server
C. Verify the vSphere Web Server service is running on the vCenter Server
D. Verify the administrator has permissions configured in vCenter Server
【单选题】
An administrator has configured an alarm to be notified when a virtual machine meets two conditions: <high virtual CPU> <high active memory consumption> The alarm is malfunctioning and triggering when either condition is met instead of both. What can be done to correct the issue? ___
A. Edit the alarm and select Trigger if ALL of the following conditions are satisfied.
B. Edit the alarm and select Trigger if ANY of the following conditions are satisfied.
C. Create two separate alarms, one for CPU and one for memory.
D. Delete the existing alarm and create a new event based alarm.
【单选题】
What must be enabled to ensure that VM Component Protection (VMCP) works in a High Availability cluster? ___
A. VMware Tools Virtual Machine Communication Interface (VMCI)
B. Fault Tolerance
C. Atomic Test and Set (ATS)
D. All Paths Down (APD) Timeout
【单选题】
An administrator wants to add a web server to an existing multi-tier application consisting of three virtual machines: <A web server> <A database server An application server> The web server should be added to the application when the primary web server reaches: <70% vCPU utilization> <55% active memory> Which option will achieve this result? ___
A. Create a virtual machine alarm with an action to run a script that starts a new instance of the web server.
B. Create a host cpu and memory alarm with an action to run a script that starts a new instance of the webserver.
C. Configure HA application monitoring for the web server and set it to trigger deployment of a new instance of the web server.
D. Configure Fault Tolerance on the virtual machine and leave the secondary machine disabled until needed.
【单选题】
An administrator has an application that requires connection directly to PCI devices through a virtual machine. What is a limitation of this configuration? ___
A. Devices must be reserved for PCI passthrough on at least one host on which the virtual machine will run.
B. Snapshots are not supported with DirectPath I/O passthrough devices.
C. A maximum of 18 PCI vSphere
D. irectPath devices can be added to a virtual machine.
【单选题】
The vSphere administrator is configuring directory services for an ESXi host: What should the vSphere administrator do to configure the host to use CAM services? ___
A. Check the Use vSphere Authentication Proxy checkbox.
B. Set Select Directory Service Type to CAM services.
C. Specify CAM$ for the
D. omain.
【单选题】
Which statement is true regarding the licensing of vCenter Server? ___
A. The license for vCenter Server must be provided at the time of installation.
B. Changing the license assigned to vCenter Server requires a restart of the vCenter Server service.
C. Virtual machines can still be powered on if the vCenter Server license expires.
D. Licensing for a single vCenter Server installation is determined by the number of managed virtual machines.
【单选题】
When configuring vSphere Replication for a virtual machine, what is the lowest Recovery Point Objective (RPO) that can be selected? ___
A. 1 min
B. 5 min
C. 10 min
D. 15min
【单选题】
A developer needs to create a multi-tier development stack for a home lab. Which vSphere product will support the architecture required for the least software cost? ___
A. vSphere Hypervisor
B. vSphere Essentials
C. VMware Player
D. VMware Workstation
【单选题】
An administrator is installing Windows into a virtual machine. The DVD has been mounted on the Host and configured for the virtual machine as shown in the Exhibit. Based on the exhibit, when the virtual machine is booted, why would it attempt to search for a PXE server? ___
A. The CD/DVD device is not connected.
B. The ISO is in the incorrect storage location.
C. The OS minimum requirements have not been met.
D. The CD/DVD device is not set to Client Device.
【单选题】
What component must be installed prior to deploying a vCenter Server in vSphere 6.x? ___
A. vCenter Identity Services
B. Platform Services Controller
C. vCenter Single Sign-On
D. Client Integration Plug-In
【单选题】
What is a valid plug-in status for a plug-in that has been added to a vSphere client? ___
A. Disabled
B. Unknown
C. Stopped
D. Installed
【单选题】
Users of an application are reporting performance issues. The following performance values are observed in the vSphere Web Client: <Host CPU utilization is 90%> <Virtual Machine memory utilization is consistently greater than 90% CPU Ready values are higher than 20%> What could be the cause of the application performance issue? ___
A. The host is lacking the CPU resources required to meet the demand.
B. The host is lacking the memory resources required to meet the demand.
C. The virtual machine is lacking the CPU resources required to meet the demand.
D. The virtual machine is lacking the memory resources required to meet the demand.
【单选题】
An administrator creates an ESXi cluster using vSphere Auto Deploy. The ESXi hosts are configured to get a management IP address from a DHCP server. The administrator needs to troubleshoot the management network on one of the hosts. Which DCUI option should the administrator use to renew the DHCP lease? ___
A. Restart Management Network
B. Restore Network Settings
C. Test Management Network
D. Configure Management Network
【单选题】
An administrator is re-provisioning an ESXi host and moving it to another datacenter. Which DCUI option should the administrator use to revert the system configuration to the default settings? ___
A. Reset System Configuration
B. Rebuild Default System Configuration
C. Revert System Configuration
D. Renew Default System Configuration
【单选题】
An administrator has just completed installing an ESXi 6.x host, but doesn't know what address has been configured. Where is the ESXi host IP address configured? ___
A. RVC console
B. Direct Console User Interface
C. vSphere Web Client
D. vSphere Client
【单选题】
When is it possible to place a VMFS5 datastore in maintenance mode? ___
A. When it is a member of a Storage DRS cluster
B. When it is a member of Virtual SAN cluster
C. When it is a member of a multi-extent datastore
D. When it is a member of a Virtual Volume
【单选题】
Immediately after installing ESXi, an administrator observes that the Configure Lockdown Mode option is grayed out in the Direct Console User Interface (DCUI). What is the most likely explanation? ___
A. The host has not yet been added to a vCenter Server.
B. The BIOS on the host does not have NX/XD enabled.
C. The ESXi host is running in evaluation mode.
D. The host requires a reboot before this feature is available.
【单选题】
Immediately after installing ESXi, an administrator observes that the Configure Lockdown Mode option is grayed out in the Direct Console User Interface (DCUI). What is the most likely explanation? ___
A. The host has not yet been added to a vCenter Server.
B. The BIOS on the host does not have NX/XD enabled.
C. The ESXi host is running in evaluation mode.
D. The host requires a reboot before this feature is available.
【单选题】
Which Single Sign-On deployment mode should an administrator use for two 6.x vCenter Servers configured with linked mode? ___
A. Basic Single Sign-On with vCenter Server Heartbeat
B. Multisite Single Sign-On
C. Basic Single Sign-On
D. Single Sign-On with Linked Mode
【单选题】
What is required when changing a virtual machine name using the vSphere Web Client? ___
A. Verify connectivity to the ESXi host where the virtual machine is running and its inventory list is accessible.
B. Verify in which datastore the virtual machine resides and that you have access and its inventory list is accessible.
C. Verify that virtual machine files are stored in the same datastore and can be accessed in the datastore browser list.
D. Verify the virtual machine is not running in Fault Tolerant mode and that it is not in a Distributed Resource Scheduler cluster.
【单选题】
An administrator deploys vRealize Operations into a vSphere 6.x environment. After the deployment, the administrator notices that badges are not appearing. What is a likely cause of this behavior? ___
A. Badges do not appear until you register vRealize Operations with vCenter Server.
B. Badges do not appear until you register a vCenter Server in vRealize Operations.
C. The vRealize Operations appliance needs to be redeployed.
D. The vCenter Server appliance needs to be redeployed.
【单选题】
How are ports scaled on vSphere Standard Switches (vSS)? ___
A. Ports on a vSS can be dynamically scaled up and down.
B. Ports on a vSS can only be statically scaled up or down.
C. Ports on a vSS can only be dynamically scaled down.
D. Ports on a vSS can only be dynamically scaled up.
【单选题】
A High Availability (HA) cluster is configured to respond to a given number of host failures. The cluster contains virtual machines configured with these settings: VM1 has a 1GHz CPU reservation and no Memory reservation VM2 has a 2GHz CPU reservation and no Memory reservation VM3 has no CPU reservation and no Memory reservation . Given this information, what is the correct slot size for the cluster? ___
A. The CPU Reservation should be set to 32MHz and the memory reservation should be set to 32MB plus memory overhead.
B. The CPU reservation should be set to 1 GHz and the memory reservation should be set to 0MB plus memory overhead.
C. The CPU reservation should be set to 2 GHz, and the memory reservation should be set to 0MB plus the virtual machine memory overhead.
D. The CPU reservation should be set to 2 GHz, and the memory reservation should be set to 32MB, plus the virtual machine memory overhead.
【单选题】
An administrator is planning a vSphere infrastructure with the following specific networking requirements: <The ability to shape inbound (RX) traffic> <Support for Private VLANs (PVLANs)> <Support for LLDP (Link Layer Discovery Protocol)>. What is the minimum vSphere Edition that will support these requirements? ___
A. vSphere Essentials Plus
B. vSphere Standard
C. vSphere Enterprise
D. vSphere
E. nterprise Plus
【单选题】
When you add an ESXi 6.x host to a new Cluster, which vSphere object owns the CPU and Memory resources of the hosts? ___
A. vCenter Server
B. Datacenter
C. Cluster
D. Host
【单选题】
A user is trying to retrieve objects from a SharePoint server and finds the request is taking an excessive amount of time. An administrator tries to isolate the issue and notes the following: Application performance is poor when compared to virtual machines on other hosts. Performance improves when the virtual machine is moved to another host. The virtual machine encounters higher than expected CPU %Ready times. What conclusion can be reached regarding the performance issues for this virtual machine? ___
A. Host Power Management is directly impacting virtual machine performance.
B. The virtual machine has a large number of snapshots.
C. The Path Selection Policy for the storage device is set differently on the affected host.
D. Network I/O control is configured for the portgroup.
【单选题】
A virtual machine template is accidently removed from the vCenter Server Inventory. Which method would be used to recover the template back into the environment?___
A. Use the datastore browser to locate the template, then right click and add the .vmtx file to inventory.
B. Use the datastore browser to locate the template, then right click and add the .vmx file to inventory.
C. Using the Managed Object Browser and adding the template from the ManagedObjectReference:GuestFileManager object.
D. Using the Managed Object Browser and adding the template from the ManagedObjectReference:VirtualDiskManager object.
【单选题】
A vSphere administrator needs to backup a virtual machine that has a Microsoft SQL Server Database installed. Which solution allows for an application quiesce to occur during backup?___
A. VMware vCenter Converter
B. VMware vCenter Site Recovery Manager
C. VMware vSphere Replication
D. VMware vSphere Data Protection Advanced
【单选题】
An administrator is migrating a virtual machine from a Test cluster to a Production cluster. The two environments do not have any shared storage. What is the easiest way to accomplish this task? ___
A. Perform a Storage vMotion.
B. Perform a regular vMotion.
C. Perform a Virtual to Virtual migration.
D. Perform a backup and restore using VMware Data Protection.
【单选题】
An administrator must determine an appropriate backup solution, given these conditions: 50 of the virtual machines are in a resource pool named Finance. 50 of the virtual machines are in a resource pool named QA. Which solution allows an administrator the ability to backup 100 virtual machines? ___
A. Use Snapshot Manager on the vCenter Server to backup the virtual machines.
B. Use the VMware Consolidated Backup (vcb) tool on the ESXi Host to backup the virtual machines.
C. Use the VMware Data Recovery (VDR) Appliance on the vCenter Server to backup the virtual machines.
D. Use the VMware Data Protection (VDP) Appliance on one of the
E. SXi Hosts to backup the virtual machines.
【单选题】
What is a benefit of using Enhanced vMotion Compatibility for an environment? ___
A. EVC masks CPU features to allow compatibility between hosts that are dissimilar.
B. EVC allows for cross platform vMotion to occur.
C. EVC enables Long
D. istance vMotion.
【单选题】
How many Link Aggregation Groups (LAGs) can be configured on a vSphere 6.x Distributed Switch? ___
A. 64
B. 96
C. 128
D. 256
【单选题】
How many Link Aggregation Groups (LAGs) can be configured on a vSphere 6.x Distributed Switch? ___
A. 64
B. 96
C. 128
D. 256
【单选题】
An administrator needs to verify that vMotion operations can be performed in a vSphere data center.What round trip time (RTT) latency is the maximum value that will allow vMotion operations to succeed? ___
A. 50ms RTT
B. 100ms RTT
C. 150ms RTT
D. 200ms RTT
【单选题】
A storage administrator has reported that full utilization of all bandwidth from an ESXi 6.x host is not being seen. In troubleshooting the issue, the Adapter details are shown in the Exhibit. Based on the exhibit, what is cause of the issue? ___
A. The array is not setup to use the correct multipathing policy.
B. There are no virtual machines on the ESXi host.
C. Not all links are used because a path is disabled.
D. Another path needs to be configured.
【单选题】
An administrator is migrating a powered-on virtual machine, as shown in the exhibit. Which option should be selected to perform a Storage vMotion of the VM? ___
A. Change storage only
B. Change VM compute resource only
C. Change both compute resource and storage, changing the compute resource first.
D. Change both compute resource and storage, changing the storage resource first.
【单选题】
An administrator is attempting to enable Storage I/O Control on a datastore, but it is failing. What is the likely reason for this failure? ___
A. The host is connected to a datastore is running on ESX 4.0.
B. The host is connected to a Fibre Channel storage array.
C. The datastore has multiple extents.
D. The datastore is managed by a single vCenter Server.
推荐试题
【单选题】
CCB141、项目经理发送最终的项目报告,并将产品所有权移交给运营团队,运营团队认为,由于存在缺陷,他们不能接受该产品。项目经理应该做什么?___
A. 与运营团队开会,解释产品的功能以及如何快速修复缺陷
B. 集合项目团队去讨论产品功能以及如何快速修复缺陷
C. 给运营团队展示产品签收文件
D. 将产品和文件转交给运营团队
【单选题】
CCB142、项目经理发现多位相关方不了解项目的技术方面,若要确保相关方对项目有足够的了解来提供批准,项目经理应该做什么?___
A. 计算项目将生产的利润
B. 与相关方一起审查决策影响
C. 向相关方说明商业问题
D. 向高级管理层请求了解项目技术的额外相关方
【单选题】
CCB143、项目经理获得一份政府合同,在项目执行期间,项目经理发现工作说明书不足以满足所需的工作,必须进行修改。项目经理首先应该做什么?___
A. 与主题专家开会
B. 写信给政府,指出该工作说明书是不正确的
C. 确定对项目进度计划的任何影响
D. 更新风险登记册
【单选题】
CCB144、项目经理加入一个项目,在新市场退出一款产品,项目经理计算记录所涉及的风险,以尽量减少项目失败的几率。项目经理下一步应该做什么?___
A. 与相关方讨论和评估可交付成果,并列出潜在风险
B. 评估可交付成果,并通知团队成员警惕可能的风险
C. 检查过往项目数据准备风险清单
D. 与发起人会面评估可能的风险并准备清单
【单选题】
CCB145、项目经理加入一个新的价值数百万美元的项目,要求成功实施来自各部门可交付成果,实施该项目,项目经理首先该怎么做?___
A. 拜访客户以确定所有的关键客户相关方的沟通渠道已经识别
B. 进行相关方分析以及详细的需求分析
C. 快速识别为项目工作的最好资源
D. 同已经成功交付过类似可交付物的外部供应商签订合同
【单选题】
CCB146、项目经理使用紧前关系绘图法为新项目制定进度计划,项目的成功取决于使用政府颁发特殊环境许可证的设备。项目经理应该做什么以确保正确的活动排序?___
A. 应用滚动式规划和专家判断
B. 考虑外部依赖关系,并包含提前量和滞后量
C. 更新风险登记册,并建立减轻策略
D. 考虑酌情依赖,更新风险清单
【单选题】
CCB147、项目经理收到将影响项目范围的变更请求批准,一个主要相关方不同意这项变更,并提出一个权变措施,这项措施将对项目的成本和进度产生较小的影响。项目经理应该做什么?___
A. 评估该权变措施对成本和进度的影响
B. 实施该权变措施
C. 更新绩效基准,并实施批准的变更
D. 请求变更控制委员会(CCB)批准该权变措施
【单选题】
CCB148、项目经理在收到项目发起人的项目章程后,发现一个众所周知的遗漏:高层级风险没有包含在项目章程中,此时项目经理应该做什么?___
A. 将高层级风险添加进工作说明书
B. 执行整体变更控制
C. 同发起人讨论该问题
D. 修订风险管理计划以涵盖该风险
【单选题】
CCB149、项目经理正在管理一个交付新车型的项目,项目工程师告知项目经理必须包含一个额外的安全元素,项目经理将该安全元素添加到需求跟踪矩阵,并开始执行项目,客户通知项目经理他们将不会为该项新功能付款。若要避免这个问题,项目经理应该事先做什么?___
A. 将该需求添加到范围说明书
B. 同变更控制委员会说明此项需求
C. 提交包含新需求的变更请求
D. 从需求跟踪矩阵排除该需求直到口头批准得到接受
【单选题】
CCB150、项目经理正在启动一个项目,该项目是之前一个项目的后续阶段,在审查经验教训登记册时,项目经理发现,由于客户未验收可交付成果,上一个阶段没有正式关闭。项目经理应该做什么?___
A. 为上一个阶段执行收尾
B. 假设前一个项目即将收尾,继续下一个项目
C. 拒绝项目,因为它可能会像前一个项目一样失败
D. 执行项目风险分析
【单选题】
CCB151、项目经理正在为一个项目工作,该项目由于人员流动,相关方登记则经常发生变化,若要内部相关方都能了解他们的职责,项目经理应该做什么?___
A. 定期与所有相关方召开面对面会议
B. 确保更新和沟通相关方管理计划
C. 只要新的相关方加入项目就安排一次团建活动
D. 在下一次团建会上安排相关方正式介绍自己
【单选题】
CCB152、项目经理正在为一家有延迟项目和变更进度计划历史的公司制定成本管理计划,作为公司文化的部分,通常为此类变更分配额外资金,考虑到所有已知和未知成本后,项目超出预算并可能延迟。项目经理应该做什么?___
A. 审查进度,看是否有压缩进度的机会
B. 让发起人考虑这样情况,并在项目章程中包含更多资金
C. 进行备选方案分析并重新审视任务以减少项目成本
D. 与关键相关方开会,审查项目挣值(EV)并减少项目成本
【单选题】
CCB153、项目经理准备了一份图表,记录缺陷并容许的规格界限进行对比,项目经理使用的是哪种工具或技术?___
A. 鱼骨图
B. 直方图
C. 控制图
D. 非一致性报告
【单选题】
CCB154、项目可行性研究确定了应该创建什么产品,现在,开发与原始需求冲突的另一种产品的一项变更请求,已经获得批准,在变更请求获得批准前已进行数据分析。项目经理应该怎么做?___
A. 实施该变更请求
B. 拒绝该变更请求
C. 请求详细的数据分析报告
D. 请求新产品的可行性研究
【单选题】
CCB155、项目可交付成果已经过核实,项目经理下一步应该做什么?___
A. 安排一次检查
B. 进行趋势分析
C. 进行阶段结束审查
D. 获得客户签字
【单选题】
CCB156、项目遇到一个主要的风险,一个关键项目资源开始遵循风险应对计划解决风险,但这却妨碍该资源完成其他分配的项目任务。项目经理应该做什么?___
A. 让该资源加班
B. 同该资源的经理谈判
C. 提交一项变更请求
D. 咨询质量保证计划
【单选题】
CCB157、一个项目的计划工作预算成本为250,000美元,项目期间已执行工作预算成本为225,000美元,项目经理报告说:实际支出金额为210,000美元。此时表明项目的绩效如何?___
A. 项目落后于进度
B. 项目超前于进度
C. 项目符合进度
D. 项目目前处于关键路径上
【单选题】
CCB158、一个项目原计划持续时间为一年,但是,发起人希望项目结束日期提前一个月。项目经理首先应该做什么?___
A. 评估项目的资源可用性
B. 分析关键路径
C. 提出变更要求
D. 使用快速跟进来提前一个月完成项目
【单选题】
CCB159、一个项目正在执行中,但破坏行为正在影响进度计划,项目经理不确定如何将该问题记录在问题日志中,因为在项目开始时已经记录了这个问题。项目经理首先应该做什么?___
A. 在现有问题上更新信息
B. 在风险登记册中添加一个新风险
C. 对破坏行为执行质量审计
D. 与团队一起审查当前规划的解决方案
【单选题】
CCB160、一个新的销售点(POS)系统安装在一家商店试用,之前已经识别到这个新系统的一个欺诈性问题,试用显示纠正措施未能阻止该问题,项目经理已经将项目恢复到旧系统。项目经理现在应该做什么?___
A. 立即寻找新的纠正措施
B. 分析问题,并将其添加到问题日志中
C. 将该问题汇报给项目发起人
D. 建议该新系统没有准备好使用
【单选题】
CCB161、一家公司计划在A市设立一个新的销售办事处,为了管理这个过程,发起人任命一位项目经理,去年该经理成功地管理了B市销售办事处的设立项目,项目经理与负责B市办事处的开发公司签订合同。在项目规划阶段,项目经理应该用什么来估算活动持续时间?___
A. 类比估算
B. 制定估算
C. 三点估算
D. 储备分析
【单选题】
CCB162、一家供应商公司的几名团队成员正在现场为一个项目工作,在第一次月度项目更新会议期间,供应商的主要资源提供了有关项目状态,问题和挑战的非常详细的信息,在会议之后,一位关键相关方抱怨说:很难了解项目的整体监控状况。若要避免这个问题,项目经理应在会议之前做什么?___
A. 向所有关键相关方发送一份简短报告,总结项目的健康情况
B. 制定一份沟通管理计划,并与供应商的主要资源进行审查
C. 将会议的议程,目标和预期结果传达给所有与会者
D. 与供应商团队一起视频会议,并提供反馈意见,以澄清每个人的角色
【单选题】
CCB163、一位高级经理告诉一位新项目经理,过去的项目经常发生范围和可交付成果问题。为了尽可能提高新项目的成功概率,项目经理在规划阶段应该做什么?___
A. 与相关方一起进行专家判断
B. 调研事业环境因素
C. 回顾经验教训登记册
D. 要求发起人提供清晰的范围说明书
【单选题】
CCB164、一位相关方以在工作完成后要求提供更多可交付成果而出名,若要管理该相关方并避免返工,范围蔓延和分歧,项目经理应该做什么?___
A. 召开一次规划会议,分享相关方参与计划
B. 向各个相关方发送电子邮件,告知他们的角色与职责,并请求提供确认
C. 与每位相关方单独会面,解释他们的角色与职责
D. 召开会议以提供可交付成果,并正式记录相关方的验收
【单选题】
CCB165、一位项目经理获悉,将从拥有质量低声誉的供应商采购关键材料,若要优化质量控制成本,项目经理应该使用什么工具或技术?___
A. 控制图
B. 石川图
C. 样品测试
D. 散点图
【单选题】
CCB166、一位项目经理组长管理一个项目,该项目是关于开发一个新的产品系列,以满足某一目标消费群体,项目经理希望在这产品系列的早期开发阶段收集有用的想法和信息。项目经理应该使用什么?___
A. 名义小组技术
B. 调查
C. 头脑风暴
D. 焦点小组会议
【单选题】
CCB167、一些关键相关方不能参加预定的项目启动大会,项目负责人要求项目经理继续能举行会议,因为他们还要参加其他会议。项目经理应该做什么确保顺利召开项目启动大会,以便能够开始执行项目?___
A. 在没有太多项目负责人参与的情况下继续召开会议
B. 取消会议,并单独跟进各个相关方
C. 推迟会议,直到所有相关方和项目负责人都能参加
D. 重新安排会议,以便除项目负责人以外的所有相关方都可以参加
【单选题】
CCB168、一座受强飓风破坏的城市需要立即修复,修复项目经理接收到与监管准则相冲突的相关方需求。项目经理首先应该做什么?___
A. 修复需求以使其符合监管准则
B. 咨询项目指导委员会,让他们解决需求
C. 通知城市冲突的需求,等待调整需求
D. 更新风险登记册,继续推进当下需求
【单选题】
CCB169、因为项目团队是第一次一起工作,项目经理识别到一个可能的项目风险,为阻止争议,项目经理应该做什么?___
A. 澄清角色和职责
B. 更新风险登记册
C. 提供日常绩效反馈
D. 建立基本规则
【单选题】
CCB170、用户验收测试比进度计划落后25%,这项活动在项目的关键路径上,延迟将会严重影响项目进度,项目经理决定对这项活动进行赶工。项目经理下一步应该做什么?___
A. 更新组织过程资产和事业环境因素
B. 更新风险登记册
C. 更新问题日志
D. 召集团队开会
【单选题】
CCB171、由于可交付成果随机样本的质量偏差较大,项目团队建议根据质量标准测试所有可交付成果,变更控制委员会(CCB)批准该建议。项目经理应该更新哪一份文件?___
A. 变更管理计划
B. 项目管理计划
C. 工作说明书
D. 变更请求
【单选题】
CCB172、在测试阶段,项目经理注意到一个供应商的产品收到大量缺陷通知,因此,供应商必须生产新版本的产品,这个过程受到内部延迟影响,供应商要求基于初始版本交付的分阶段付款,为了做出支付决策,项目经理应该参考以下哪一份文件?___
A. 质量管理计划和工作说明书
B. 财务管理合同和供应商合同
C. 采购管理计划和工作说明书
D. 工作绩效信息和供应商合同
【单选题】
CCB173、在发现范围说明中未包含一项关键活动之后,发起人提交正式的变更请求将该活动添加进项目,已经完成影响评估,并收到批准。项目经理应该做什么?___
A. 参考项目章程回顾该关键活动的详细影响
B. 跟团队确认该活动对项目是否必要
C. 建议发起人启动一个新项目
D. 指示团队执行这项活动
【单选题】
CCB174、在过渡期间,处于执行阶段的一个项目失去重要的团队成员,项目经理发现新组建的团队错过了关键时期。项目经理接下来应该做什么?___
A. 确保团队配置贯穿项目始终
B. 同团队一起审查项目绩效数据
C. 审查资源管理计划
D. 为额外资源谈判
【单选题】
CCB175、在识别相关方之后,项目经理得知客户尝试变更项目范围,这使得难以制定最终的项目范围,首席执行官希望解决这种情况,避免项目延期。项目经理应该做什么?___
A. 与客户开会,根据项目管理计划商定项目计划
B. 跟CEO沟通进行初步行动的优先级排序,并调整范围管理计划
C. 跟客户说明项目范围说明书的重要性
D. 请一队专家来确定哪些条款应包含在商业论证中
【单选题】
CCB176、在项目的测试阶段,识别到一个缺陷并与项目团队沟通,一位主题专家(SME)对结果感到不满并离开项目,必须找到一位合适的主题专家才能继续项目。项目经理应使用什么工具或技术来找到一位合适的替代主题专家?___
A. 专家判断
B. 应急应对策略
C. 敏感性分析
D. 决策网分析
【单选题】
CCB177、在项目设计阶段,项目经理发现可能影响项目成本、进度、范围和质量的额外风险,若要处理这些风险,项目经理应该做什么?___
A. 准备概率影响矩阵
B. 跟相关方说明风险
C. 创建风险管理计划
D. 与团队会面讨论风险
【单选题】
CCB178、在项目执行期间,职能经理将两个关键资源重新分配给另外一个项目,项目经理失去宝贵的技能,没有足够的资源来实现下一个里程碑。若要避免这个问题,项目经理事先应该做什么?___
A. 修改资源管理计划,重新定义应如何分配,管理和解散资源的项目需求
B. 在风险登记册和问题日志的初始设置过程中考虑所有可能的风险
C. 让该职能经理参与规划过程,讨论并决定目标、范围、进度和资源需求
D. 与该职能经理讨论该项目的资源需要和项目目标
【单选题】
CCB179、在项目中途,一个挑剔的客户要求提供定期报告,包含比沟通管理计划中批准的更详细的信息,该项请求将导致生产成本超出预算,项目经理不能承受让这个客户生气的后果,但客户拒绝见面讨论此事。项目经理应该怎么做?___
A. 提醒客户相关方与计划中列出的要求并请求采取纠正措施
B. 要求在该相关方组织中有影响力的人物帮助指导客户的期望,使其与商定的计划保持一致
C. 提交变更请求以支付制作报告的额外费用
D. 接受该请求,让客户满意并更新沟通管理计划
【单选题】
CCB180、在一次项目进度会议上,项目经理发现其中一位相关方对项目非常支持并愿意提供帮助,在审查相关方登记册时,他们注意到,根据相关方的权力等级,这位相关方索引编制错误。若要正确的排列相关方的位置,项目经理应该做什么?___
A. 更新沟通管理计划,索引编制该相关方的权力等级
B. 持续进行相关方识别和评估,更新相关方登记册
C. 根据最新收集的评估信息和分类提交变更请求
D. 从以往项目中检查信息,评估相关方权力
欢迎使用我爱刷题
×
微信搜索我爱刷题小程序
温馨提示
×
请在电脑上登陆“www.woaishuati.com”使用