【单选题】
A user is trying to retrieve objects from a SharePoint server and finds the request is taking an excessive amount of time. An administrator tries to isolate the issue and notes the following: Application performance is poor when compared to virtual machines on other hosts. Performance improves when the virtual machine is moved to another host. The virtual machine encounters higher than expected CPU %Ready times. What conclusion can be reached regarding the performance issues for this virtual machine? ___
A. Host Power Management is directly impacting virtual machine performance.
B. The virtual machine has a large number of snapshots.
C. The Path Selection Policy for the storage device is set differently on the affected host.
D. Network I/O control is configured for the portgroup.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
相关试题
【单选题】
A virtual machine template is accidently removed from the vCenter Server Inventory. Which method would be used to recover the template back into the environment?___
A. Use the datastore browser to locate the template, then right click and add the .vmtx file to inventory.
B. Use the datastore browser to locate the template, then right click and add the .vmx file to inventory.
C. Using the Managed Object Browser and adding the template from the ManagedObjectReference:GuestFileManager object.
D. Using the Managed Object Browser and adding the template from the ManagedObjectReference:VirtualDiskManager object.
【单选题】
A vSphere administrator needs to backup a virtual machine that has a Microsoft SQL Server Database installed. Which solution allows for an application quiesce to occur during backup?___
A. VMware vCenter Converter
B. VMware vCenter Site Recovery Manager
C. VMware vSphere Replication
D. VMware vSphere Data Protection Advanced
【单选题】
An administrator is migrating a virtual machine from a Test cluster to a Production cluster. The two environments do not have any shared storage. What is the easiest way to accomplish this task? ___
A. Perform a Storage vMotion.
B. Perform a regular vMotion.
C. Perform a Virtual to Virtual migration.
D. Perform a backup and restore using VMware Data Protection.
【单选题】
An administrator must determine an appropriate backup solution, given these conditions: 50 of the virtual machines are in a resource pool named Finance. 50 of the virtual machines are in a resource pool named QA. Which solution allows an administrator the ability to backup 100 virtual machines? ___
A. Use Snapshot Manager on the vCenter Server to backup the virtual machines.
B. Use the VMware Consolidated Backup (vcb) tool on the ESXi Host to backup the virtual machines.
C. Use the VMware Data Recovery (VDR) Appliance on the vCenter Server to backup the virtual machines.
D. Use the VMware Data Protection (VDP) Appliance on one of the
E. SXi Hosts to backup the virtual machines.
【单选题】
What is a benefit of using Enhanced vMotion Compatibility for an environment? ___
A. EVC masks CPU features to allow compatibility between hosts that are dissimilar.
B. EVC allows for cross platform vMotion to occur.
C. EVC enables Long
D. istance vMotion.
【单选题】
How many Link Aggregation Groups (LAGs) can be configured on a vSphere 6.x Distributed Switch? ___
A. 64
B. 96
C. 128
D. 256
【单选题】
How many Link Aggregation Groups (LAGs) can be configured on a vSphere 6.x Distributed Switch? ___
A. 64
B. 96
C. 128
D. 256
【单选题】
An administrator needs to verify that vMotion operations can be performed in a vSphere data center.What round trip time (RTT) latency is the maximum value that will allow vMotion operations to succeed? ___
A. 50ms RTT
B. 100ms RTT
C. 150ms RTT
D. 200ms RTT
【单选题】
A storage administrator has reported that full utilization of all bandwidth from an ESXi 6.x host is not being seen. In troubleshooting the issue, the Adapter details are shown in the Exhibit. Based on the exhibit, what is cause of the issue? ___
A. The array is not setup to use the correct multipathing policy.
B. There are no virtual machines on the ESXi host.
C. Not all links are used because a path is disabled.
D. Another path needs to be configured.
【单选题】
An administrator is migrating a powered-on virtual machine, as shown in the exhibit. Which option should be selected to perform a Storage vMotion of the VM? ___
A. Change storage only
B. Change VM compute resource only
C. Change both compute resource and storage, changing the compute resource first.
D. Change both compute resource and storage, changing the storage resource first.
【单选题】
An administrator is attempting to enable Storage I/O Control on a datastore, but it is failing. What is the likely reason for this failure? ___
A. The host is connected to a datastore is running on ESX 4.0.
B. The host is connected to a Fibre Channel storage array.
C. The datastore has multiple extents.
D. The datastore is managed by a single vCenter Server.
【单选题】
A mission-critical virtual machine built on vSphere 4.1 needs to be moved to an ESXi 6.x host.Which virtual hardware version is needed to move the virtual machine without upgrading? ___
【单选题】
An administrator is analyzing a virtual machine as shown in the Exhibit. What is the current long term risk for this virtual machine? ___
A. The virtual machine may run out of memory before April 27.
B. The virtual machine may continue to function after April 27.
C. The virtual machine has adequate memory configured for operation for the next 120 days.
D. The virtual machine has adequate memory reservation configured for operation for the next 120 days.
【单选题】
An administrator is monitoring a High Availability (HA) and Distributed Resource Scheduler (DRS) enabled cluster and has noticed that virtual machines in the cluster are being migrated without user intervention. Why is this happening? ___
A. The DRS Automation level is set to Fully Automated.
B. The Automation level is set to Automatic.
C. The
D. PM Threshold is set to Aggressive.
【单选题】
An administrator attempts to migrate a suspended virtual machine to a newly deployed vSphere 6.x cluster. The compatibility check fails. What condition could cause this behavior?___
A. The new vSphere 6.x cluster is running Intel CPUs instead of AMD CPUs.
B. A suspended virtual machine cannot be migrated.
C. The hardware virtualization feature of the CPU is not enabled on the new hosts.
D. A vSphere Distributed Switch is required to migrate a suspended virtual machine.
【单选题】
A vSphere administrator has been using vSphere in evaluation mode and now wants to deploy an environment that provides the same features. Which edition of vSphere provides similar functionality to evaluation mode? ___
A. Enterprise Plus
B. Enterprise
C. Standard
D. Essentials
【单选题】
A vSphere administrator has been using vSphere in evaluation mode and now wants to deploy an environment that provides the same features. Which edition of vSphere provides similar functionality to evaluation mode? ___
A. Enterprise Plus
B. Enterprise
C. Standard
D. Essentials
【单选题】
An administrator has just configured the IP address on an ESXi host from the Direct Console User Interface. How can the configuration be validated as correct without any additional tools?___
A. Add the host to vCenter Server and if it works, then all networking settings are ok.
B. Select the Test Management Network option from the DCUI.
C. Connect to the host with the vSphere Client and click the Test Network option.
D. Use PowerCLI to connect to the host and initiate a network test.
【单选题】
An administrator is installing vCenter Server for an environment that has 40 ESXi 6.x Hosts and 150 virtual machines. Which database would meet the minimal requirements needed for this task? ___
A. vFabric Postgres
B. Microsoft SQL Express 2008
C. Microsoft SQL Server 2014
D. Oracle 11g
【单选题】
What is a requirement when enabling a Virtual SAN cluster in an existing High Availability (HA) and Distributed Resource Scheduler (DRS) Cluster? ___
A. Disable DRS and HA before enabling Virtual SAN
B. Enable DRS before enabling Virtual SAN
C. Disable HA before enabling Virtual SAN
D. Enable Storage DRS before enabling Virtual SAN
【单选题】
The vSphere administrator attempts to connect to an ESXi host via an SSH client and receives the following security alert: The vSphere administrator needs to determine whether the RSA key fingerprint shown in the security alert is the fingerprint of the intended ESXi host. Which tool should the vSphere administrator use? ___
A. Direct Console User Interface
B. vSphere Client
C. vSphere Web Client
D. vSphere Management Assistant
【单选题】
An administrator needs to monitor traffic on vSwitches in a vSphere 6.x environment. Which option, if configured, would accomplish this task? ___
A. Forged Transmits
B. MAC Address Changes
C. Promiscuous Mode
D. Notify Switches
【单选题】
What is true regarding datastores on ESXi 6.x? ___
A. NFS 4.1 datastore does not support Fault Tolerance (FT)
B. VMFS3 and VMFS5 datastores can be newly created
C. NFS datastore can be concurrently mounted using NFS 4.1 on one host and NFS on another
D. NFS 3.0 datastore does not support Fault Tolerance (FT)
【单选题】
An administrator is cloning and configuring five new web server virtual machines. What would be the benefit of configuring resource shares for the new VMs? ___
A. To prioritize access to a resource during contention.
B. To guarantee access to a resource during contention.
C. To prioritize access to a resource before contention occurs.
D. To guarantee access to a resource before contention occurs.
【单选题】
An administrator logs into the vSphere Web Client and sees the warning shown in the Exhibit. During a change control window, the warning was addressed. What should be done to verify that the host is no longer showing the warning? ___
A. Run a Remediate host operation.
B. Recheck the compliance of the host.
C. Restart the host to get rid of the warning.
D. Install VMware tools to clear the warning.
【单选题】
A vApp named Sales has a Memory Limit of 32 GB and a CPU Limit of 12,000 MHz. There are three virtual machines within the vApp: <Sales-DB -- Has a memory reservation of 20 GB. > <Sales-DC -- Has a memory reservation of 8 GB. > <Sales-Web -- Has a memory reservation of 8 GB.> Which statement is correct? ___
A. All three virtual machines can power on, but will have memory contention.
B. All three virtual machines can power on without memory contention.
C. Only two of the three virtual machines can power on.
D. Only one of the virtual machines can power on.
【单选题】
You are editing the management network configuration of an ESXi 6.x Host from the vSphere Web Client. You mistakenly put the incorrect VLAN in place for the management network. What action do you need to take to correct this? ___
A. You need to manually edit the configuration on the host with command line utilities.
B. No action is required. By default ESXi rolls back configuration changes that disconnect the host.
C. The ESXi host system configuration will need to be restored to the factory configuration to fix the issue.
D. The change can be reverted in the vSphere Web Client by simply editing the switch again.
【单选题】
What is true about resource pools created on a Distributed Resource Scheduler (DRS) cluster?___
A. A root resource pool is created with the specified values.
B. A root resource pool is automatically created using the aggregate total of the ESXi host resources in the cluster.
C. A root resource pool is automatically created using the aggregate total of all resources in the datacenter.
D. A root resource pool is not needed when creating resource pools on a DRS cluster.
【单选题】
An administrator attempts to enable Enhanced vMotion Compatibility (EVC) on a cluster. The operation results in a compatibility error, as shown in the exhibit. What is the likely cause of this error? ___
A. The CPUs in the ESXi host are not AMD CPUs.
B. The CPUs in the ESXi host do not support hardware virtualization capabilities.
C. The XD/NX CPU features have not been enabled in the BIOS of the server.
D. There is no shared storage between the hosts in the cluster.
【单选题】
What condition would prevent an administrator from creating a new VMFS3 datastore on an ESXi 6.x host using the vSphere Web Client? ___
A. A VMFS3 datastore cannot be created on an ESXi 6.x host.
B. The VMFS3 kernel module is not loaded.
C. A VMFS3 datastore cannot be mounted on an ESXi 6.x host.
D. VMFS3 datastores are not compatible with virtual machines created on an
E. SXi 6.x host.
【单选题】
During a new vSphere Distributed Switch configuration, where does the Maximum Transmission Unit (MTU) value get modified? ___
A. Uplink Settings
B. Switch Settings
C. Portgroup Settings
D. NIC Teaming Settings
【单选题】
A small company wants to use VMware products for its production systems. The system administrator needs to recommend a solution that will deliver High Availability to the company's production applications. What is minimum vSphere offering that will support this requirement? ___
A. vSphere Essentials
B. vSphere Essentials Plus
C. vSphere Hypervisor
D. vSphere Standard
【单选题】
Which scenario shows a reason for VMware Tools failing to install? ___
A. Virtual machine has a CD-ROM configured.
B. Guest OS Antivirus is blocking the VMware Tools installation.
C. Guest OS has 64-bit ldd (list dynamic dependencies) utility installed.
D. Virtual machine is powered on.
【单选题】
An administrator is configuring an ESXi 6.x host to use multiple NICs to resolve a management network redundancy error. After configuring a second NIC, the server is not able to communicate when the primary connection is taken down. The administrator analyzes the Exhibit shown here. Based on the exhibit, what is the likely cause of the issue? ___
A. vmnic4 is not attached to a vSwitch.
B. vmnic2 is not connected to a physical switch.
C. E1000 is the incorrect NIC
D. river for this card.
【单选题】
What information is required as part of an interactive ESXi 6.x installation? ___
A. Keyboard layout
B. IP Address
C. Root password
D. DNS information
【单选题】
What is the default load balancing policy for a newly created VMkernel port on a vSphere Distributed Switch? ___
A. Route based on orginating virtual port ID
B. Route based on IP Hash
C. Route based on source mac address
D. Route based on physical NIC load
【单选题】
An administrator deploys vCenter Server using the embedded Platform Services Controller. After testing the deployment for a couple of months, it is determined that the environment would be better served with an external Platform Services Controller. What should the administrator do to meet this new requirement? ___
A. Deploy a fresh instance of vCenter Server with an external Platform Services Controller.
B. Perform a fresh install of an external Platform Services Controller.
C. Migrate the embedded Platform Services Controller to an external Platform Services Controller.
D. Upgrade the embedded Platform Services Controller to an external Platform Services Controller.
【单选题】
Why are some virtual machines orphaned after rebooting a High Availability (HA) enabled host? ___
A. The Orphaned virtual machines have HA restart disabled.
B. The Orphaned virtual machines moved recently and the change did not persist.
C. The host is attached to failed storage.
D. The host just came out of maintenance mode.
【单选题】
Which vSphere 6 Standard Edition feature will allow an organization to ensure that critical multi-threaded applications have the maximum possible uptime? ___
A. Fault Tolerance
B. High Availability
C. Distributed Resource Scheduler
D. App HA
【多选题】
An application running in a virtual machine is experiencing performance issues. When utilizing performance monitoring utilities, it is noted that the CPU Utilization of the application is at 100%. Which two scenarios are probable causes of the CPU contention for the application? (Choose two.)___
A. There is a network I/O constraint.
B. There is a storage I/O constraint.
C. There is insufficient disk space assigned to the virtual machine.
D. The application is not virtualization aware.
推荐试题
【单选题】
以下哪项不是质量测量指标的例子? ( }
A. 识别的缺陷数量, 每月总停机时间
B. 客户满意度分数, 每个代码行的错误
C. 测试覆盖度, 故障率
D. 统计抽样的频率
【单选题】
下列关于过程分析的说法, 不正确的是 ( )。
A. 过程分析可以识别出过程改进的机会
B. 过程分析在管理质量过程中使用
C. 需要分析在过程运行期间遇到的问题和制约因素, 以及发现的非增值活动
D. 过程分析旨在实现跨越式的改进, 把产品质量做得超过要求
【单选题】
以下哪项不是管理质量过程中使用的数据分析技术? ( )
A. 备选方案分析
B. 文件分析
C. 过程分析
D. 多标准决策分析
【单选题】
产品交给客户使用后, 团队对客户开展满意度问卷调查。 问卷调查中识别的缺陷相关成本将会 ( )。
A. 被视为外部失败成本
B. 被视为内部失败成本
C. 对组织没有太大影响
D. 是沉没成本
【单选题】
保证在生产过程中不出现错误, 这是对下列哪个概念的解释? ( )
【单选题】
质量是指 ( )。
A. 符合三重制约
B. 符合要求
C. 优于同类产品
D. 产品的功能众多
【单选题】
以下关于项目质量管理的说法错误的是 ( )。
A. 项目质量管理既要考虑项目管理的质量, 又要考虑项目产品的质量
B. 项目质量管理同时兼顾项目过程的质量和项目结果的质量
C. 项目质量管理方法适用于所有的项目, 无论项目会产出怎样的结果
D. 项目质量管理是为了保证项目结果达到尽可能高的质量标准
【单选题】
项目团队想通过一种更加客观和结构化的方法, 找出产品存在的缺陷、 漏洞和其他不合规问题, 可以使用以下哪项技术? ( )
A. 检查
B. 审计
C. 测试或产品评估
D. 统计抽样
【单选题】
资源管理中, 以下哪项管理过程不会造成事业环境因素的更新?( )
A. 获取资源
B. 建设团队
C. 管理团队
D. 控制资源
【单选题】
可以使用以下哪种结构来把组织中的部门与项目中的工作包联系起来 ? ( )
A. 工作分解结构
B. 资源分解结构
C. 风险分解结构
D. 组织分解结构
【单选题】
以下哪项不是团队章程的内容? ( )
A. 团队价值观
B. 沟通指南
C. 会议指南
D. 团队建设
【单选题】
责任分配矩阵具有以下作用, 除了( )
A. 反映与每个人有关的所有活动
B. 反映与每个活动有关的所有人
C. 为每个工作指定唯一责任点
D. 使每个人都只负责一项工作
【单选题】
规划资源管理过程的输出包括
A. 团队绩效评价
B. 项目团队资源管理
C. 项目组织图
D. 资源管理计划
【单选题】
高效的项目团队应该 ( )。
A. 以领导为导向
B. 以任务和结果为导向
C. 集中办公
D. 通过电子网络联系
【单选题】
通过审查项目绩效评估文件, 以及与团队成员进行交谈, 项目经理发现需要开展一项计划外的技能培训, 接下来他应该 ( )。
A. 什么也不做, 只能按计划开展培训
B. 动用管理储备开展计划外培训
C. 向组织申请计划外的培训费用
D. 压缩其他培训费用
【单选题】
项目已经启动, 刚刚进入计划编制阶段。 在计划编制阶段的早期, 项目经理通常应该采用什么领导风格? ( )
A. 命令式
B. 教练型
C. 支持型
D. 授权型
【单选题】
项目的早期, 应该让哪些人参与项目的规划和决策? ( )
A. 少数技术专家
B. 项目经理
C. 核心团队成员
D. 所有项目团队成员
【单选题】
关于认可与奖励, 下列说法错误的是 ( )。
A. 在决定认可与奖励时, 应考虑文化差异
B. 认可与奖励应该在项目结束之后做
C. 只有满足被奖励者的某个重要需求的奖励, 才是有效的奖励
D. 除了金钱奖励, 还存在各种有效的无形奖励
【单选题】
以下哪项不是管理团队过程的输出? ( )
A. 项目文件更新
B. 事业环境因素更新
C. 项目管理计划更新
D. 团队绩效评价
【单选题】
项目即将结束, 为了减轻团队成员的焦虑情绪, 让团队成员向新项目平滑过渡,项目经理应该 ( )
A. 按资源管理计划执行
B. 提前遣散团队成员
C. 做好人力资源风险控制
D. 对团队成员进行培训
【单选题】
人员的预分派不适用于 ( )
A. 在投标文件中所指定的人员
B. 具有特定的知识和技能的人员,项目因他们而存在
C. 项目章程中指定的项目经理
D. 根据雇佣合同就位的优秀专业人员
【单选题】
为了获得项目所需的人力资源, 项目经理经常要与以下各方谈判, 除了 ( )。
A. 高级管理层
B. 职能部门经理
C. 其他项目经理
D. 外部资源供应商
【单选题】
采取虚拟团队的方式开展项目工作, 其优势是 ( )
A. 团队成员之间更容易分享知识和经验
B. 更容易跟进项目进度
C. 可有效利用各个地区专家的力量
D. 在家办公的团队成员容易产生孤立感
【单选题】
完成一个大型复杂项目后, 项目经理向组织争取到原来的团队成员继续开展下一个新项目。 在新项目上, 项目团队建设将 ( )。
A. 按五个阶段依次进行
B. 停滞在规范阶段
C. 跳过震荡阶段
D. 退回到解散阶段
【单选题】
在项目环境中,冲突是不可避免的,会因各种原因而产生。冲突最常见的来源由多到少排列为 ( )
A. 成员个性、 资源稀缺、 进度优先级排序
B. 进度优先级排序、 资源稀缺、 成员个性
C. 资源稀缺、 进度优先级排序、 成员个性
D. 资源稀缺、 进度优先级排序、 个人工作风格
【单选题】
可以用以下哪种格式来记录团队成员的详细职责? ( )
A. 组织分解结构
B. 责任分配矩阵
C. RACI 矩阵
D. 文本型,
【单选题】
在弱矩阵中, 项目经理对团队成员只有很小的命令职权, 使用哪种技能对项目成功非常关键? ( )
A. 领导力
B. 决策能力
C. 冲突管理能力
D. 影响力
【单选题】
为了成功激励一个由高学历、 高素质人才组成的科技团队, 项目管理者可以用下面哪些激励理论?( )
A. 期望理论和 X 理论
B. X 理论和马斯洛需求层次理论
C. Y 理论和赫兹伯格的激励因素理论
D. 赫兹伯格的保健因素理论, 以及期望理论
【单选题】
在矩阵式管理之下, 项目经理应该如何取得项目所需的人力资源?( )
A. 指令职能部门经理提供所需的人力资源
B. 从执行组织外部招聘尽可能多的人力资源
C. 直接向职能部门中的员工发出加入项目团队的邀请信
D. 与职能部门经理就所需人力资源进行谈判
【单选题】
评价项目团队有效性的指标包括 ( )。
A. 个人技能的改进、 团队能力的改进、 成员离职率下降、 团队凝聚力提高
B. 项目经理的权威加强、 团队能力的改进、 成员离职率下降、 团队凝聚力提高
C. 个人技能的改进、 团队能力的改进、 团队凝聚力提高、 项目业绩提高
D. 团队能力的改进、 成员离职率下降、 团队凝聚力提高、 项目业绩提高
【单选题】
项目经理希望发布团队章程, 对项目团队的可接受行为做出明确规定, 他应该 ( )
A. 亲自编制团队章程, 下发给团队成员执行
B. 确保团队章程的权威性, 一旦发布不得修改
C. 在建设团队过程中开始编制项目章程
D. 用团队章程指导新成员融人团队
【单选题】
确保在正确的时间把正确的资源用到正确的地方, 提高资源的使用效率和效果, 并且在不需要时被释放。 这是以下哪个管理过程的主要作用?( )
A. 控制资源
B. 建设团队
C. 管理资源
D. 估算活动资源
【单选题】
具有共同目标, 通常不面对面工作, 而是依靠电子通信工具相互联系的一群人, 被称为 ( )。
A. 项目团队
B. 虚拟团队
C. 虚假团队
D. 项目管理团队
【单选题】
以下哪项是按资源的类别和类型两个维度做的层级分解结构? ( )
A. 资源需求
B. 估算依据
C. 资源分解结构
D. 责任分配矩阵
【单选题】
在 RACI 责任分配矩阵中, 应该为每一项工作指定 ( )。
A. 唯一的最终责任人
B. 两个最终责任人, 以便相互帮助
C. 三个最终责任人, 以便集体领导
D. 一个或以上的最终责任人, 视具体情况而定
【单选题】
尽管项目团队的氛围很好, 但大家对项目的具体目标和各种问题还缺少了解。这个团队处于团队发展过程的哪一个阶段? ( )
A. 形成阶段
B. 震荡阶段
C. 规范阶段
D. 成熟阶段
【单选题】
以下哪项是资源管理计划的内容?( )
A. 资源需求
B. 资源分解结构
C. 角色与职责
D. 团队的决策标准和过程
【单选题】
在管理项目团队时, 项目经理处理冲突的基本思路是 ( )。
A. 冲突以项目经理协调为主, 这样能尽快解决冲突, 不影响项目目标
B. 团队成员之间的冲突, 应该由他们自己解决, 项目经理不宜介人
C. 采取正式程序或惩戒措施, 对化解冲突是不利的
D. 先由冲突当事人尽早自己解决冲突, 必要时再由项目经理提供帮助。如果破坏性冲突继续存在, 就采取强制措施。
【单选题】
在项目资源管理中, 跟踪团队成员的表现, 提供反馈, 管理冲突并解决问题。 这是在哪个管理过程组开展的?( )
A. 规划过程组
B. 执行过程组
C. 监控过程组
D. 收尾过程组
【单选题】
在制订资源管理计划时, 往往需要使用资源直方图说明什么时候需要多少资源。 资源直方图中的基本要素包括 ( )
A. 表示时间的横轴
B. 表示各时段所需资源数量的柱子
C. 表示可用的最大资源数量的横线
D. 以上都是