【单选题】
Assuming a mirrored (RAID-1) object configuration, how many hosts must contribute storage in a non-stretched VMware vSAN cluster to satisfy the “Number of failures to tolerate” policy option?“n” is the desired “Number of failures to tolerate” value for all options.___
A. 2n+2
B. 2n
C. 2n+1
D. 3n
查看试卷,进入试卷练习
微信扫一扫,开始刷题
答案
C
解析
暂无解析
相关试题
【单选题】
An administrator must change the statistics level for short-term performance monitoring and wants to collect metrics for all counters, excluding minimum and maximum rollup values. What would be the statistics level?___
A. Level 3
B. Level 1
C. Level 2
D. Level 4
【单选题】
In a vSphere environment, two resource pools are created as shown in the Exhibit. Each VM is configured with 1 GB of memory. When the administrator tried to power on VM3, the operation failed. What action in the resource pool settings will allow VM3 to power on successfully?___
A. Deselect Expandable Memory Reservation
B. Increase Memory Reservation
C. Deselect Expandable CPU Reservation
D. Increase the CPU Reservation
【单选题】
Which network is used by vSphere HA when VMware vSAN is enabled?___
A. Management network
B. vSphere Replication network
C. vMotion network
D. VSAN network
【单选题】
Which statement is correct when migrating from a Windows vCenter Server to the vCenter Server Appliance 6.5?___
A. Migration deployments do not migrate local OS users from the source vCenter Server.
B. Migration deployments support DHCP on the source vCenter Server.
C. Migration deployments allow the source vCenter Server to remain powered on afterwards.
D. Migration deployments support custom ports for all services on the source vCenter Server.
【单选题】
How can failback of a recovered virtual machine in vSphere Replication be performed?___
A. No action required, because failback is automatically performed to the source site.
B. Configure a new replication in the reverse direction at the target site.
C. Disable or Stop the virtual machine replication on the source site.
D. Power off and unregister the virtual machine on the target site.
【单选题】
After upgrading the vSphere infrastructure and VMware Tools to version 6.5, the “Upgrade VM Compatibility” option is grayed out in the vSphere Web Client. (See Exhibit.) What must the administrator do to enable the VM compatibility upgrade?___
A. VMware Tools should be upgraded last.
B. Restart the ESXi server.
C. Uninstall VMware Tools.
D. Power off the virtual machine.
【单选题】
What availability mode does vCenter HA provide?___
A. Active-Passive
B. Active-Standby
C. Active-Active
D. Load-balanced
【单选题】
In which scenario will vSphere DRS balance resources when set to Fully Automated?___
A. Hosts with only shared storage
B. Hosts are part of a vSphere HA cluster
C. Power Management is set to Balanced on hosts
D. Hosts with shared or non-shared storage
【单选题】
What VMware technology can be used to move physical servers to the vSphere infrastructure?___
A. VMware vMotion
B. VMware Converter
C. VMware vCenter Server
D. OVF transport
【单选题】
Upgrading vCenter Server with Microsoft SQL database fails with the following error message: The DB User entered does not have the required permissions needed to install and configure vCenter Server with the selected DB. Please correct the following error(s): %sWhat could cause this error?___
A. incorrect ports open on SQL Server
B. incorrect database on the SQL server
C. incorrect compatibility mode on the SQL server
D. incorrect permission on SQL Server database
【单选题】
What is a potential downside of having more than four paths per datastore?___
A. limits the storage protocols
B. increases storage latency for VM
C. limits the path selection policies
D. limits the number of LUNs per host
【单选题】
Which feature facilitates the sharing of templates via vCenter Server?___
A. Content Library
B. OVF
C. folders
D. vApp
【单选题】
A vSphere Administrator is in the process of configuring replication for a virtual machine, but is not able to select the Recovery Point Objective (RPO) value of 5 minutes. Which statement could explain why the RPO value cannot be lower than 15 minutes?___
A. The OS quiescing option is selected for Replication options.
B. The virtual machine hardware version is not compatible.
C. The target and source sites use different types of datastores.
D. The target and source sites are not using VMFS 6.0 datastore.
【单选题】
What advanced parameter defines a custom isolation IP address for a vSphere HA cluster?___
A. das.usedefaultisolationaddress
B. das.isolationshutdowntimeout
C. fdm.isolationpolicydelaysec
D. das.isolationaddress
【单选题】
Which method is supported for backing up the virtual machine that contains vCenter Server?___
A. differential
B. incremental
C. full image
D. individual disks
【单选题】
A vSphere Administrator must ensure that a user is able to view and manage the system configuration in vSphere Web Client. In the vCenter Single Sign-On domain, which group should the user be a part of?___
A. SystemConfiguration.BashShellAdministrators
B. ComponentManager. Administrators
C. Administrators
D. SystemConfiguration.Administrators
【单选题】
What is the minimum number of hosts that must contribute capacity to a non-ROBO single site VMware vSAN cluster?___
A. 1
B. 64
C. 3
D. 2
【单选题】
Which guest operating system supports PVRDMA?___
A. Windows (32-Bit)
B. Linux (32-Bit)
C. Windows (64-Bit)
D. Linux (64-Bit)
【单选题】
What is the correct way to replace the certificate on an existing vCenter Server that is part of a vCenter HA configuration?___
A. Put the vCenter HA in Maintenance mode, replace the certificate, exit Maintenance mode.
B. Shut down Passive and Witness nodes and replace the certificate on the Active node.
C. Remove the Passive and Witness nodes, replace the certificate, reconfigure the cluster.
D. Replace the certificate while all nodes are participating in the cluster.
【单选题】
The vSphere Data Protection performance analysis results in the “Conditionally Passed” status. What can cause this condition?___
A. The results did not meet the minimum performance expectations.
B. The read, write, and seek tests were successful.
C. The read and write tests were successful but the seek test failed.
D. The read and write tests were successful but the seek test skipped.
【单选题】
A vSphere Administrator wants to reserve 0.5 Gbps for virtual machines on each uplink on a disturbed switch that has 10 uplinks. What is the quota that should be reserved for the network resource pool?___
A. 10 Gbps
B. 5 Gbps
C. 100 Gbps
D. 0.5 Gbps
【单选题】
A vSphere administrator manages a cluster which includes critical and non-critical virtual machines. The cluster requires different permissions for contractors and non-contractors. How can the administrator exclude the contractor group from some of the critical VMs?___
A. Apply permission for both contractors and non-contractors on the cluster level.
B. Apply permission for both contractors and non-contractors on the cluster level. Remove permission on the critical VMs for contractors.
C. Remove permission for contractors on the cluster level. Apply permission on the critical VMs for noncontractors.
D. Apply permission for both contractors and non-contractors on the VMs. Remove permission on the critical VMs for contractors.
【单选题】
In an ESXi 6.5 cluster only "NFS datastore has running or registered virtual machines" returns. A vSphere HA cluster with four hosts has admission control configured to tolerate one host failure. Which statement is true if a fifth host is added?___
A. CPU and Memory capacity will be set to 50%.
B. CPU and Memory capacity will be set to 30%.
C. CPU and Memory capacity will be set to 25%.
D. CPU and Memory capacity will be set to 20%.
【单选题】
Which command can be run to troubleshoot connectivity problems with vmkernal network interfaces?___
A. esxcli network
B. vmkping
C. net-status
D. vicfg-vmknic
【单选题】
What counter should an administrator check to determine if a virtual machine is ballooning?___
A. swapinRate
B. vmmemctltarget
C. swapped
D. vmmemctl
【单选题】
By default, how often is the vCenter vpx user password automatically changed?___
A. 15 days
B. 60 days
C. 30 days
D. 45 days
【单选题】
Which metric in the Exhibit would identify high latency for a virtual machine operating system?___
A. QAVG/cmd
B. KAVG/cmd
C. DAVG/cmd
D. GAVG/cmd
【单选题】
What VM Monitoring setting would ensure that the failure interval for a virtual machine is defined as 120 seconds?___
A. High
B. Normal
C. Low
D. Medium
【单选题】
The business managers have asked the IT administrator to ensure configuration compliance in the vSphere infrastructure. The IT administrator wants to use Host Profiles to accomplish this, but is unable to do so. Why is the administrator unable to use Host Profiles?___
A. The infrastructure uses a vSphere Standard license.
B. The infrastructure has servers with various CPU families.
C. The user has only the “Administrator” role.
D. Host Profiles apply only to storage settings.
【单选题】
What is the result of a “Consolidate” action on a virtual machine?___
A. All snapshots on the virtual machines will be deleted.
B. The virtual machine will be reverted to its last snapshot.
C. Redundant delta disks will be combined and deleted.
D. A new snapshot with memory state will be created.
【单选题】
A Telco customer is implementing NFV using vSphere as the virtualization platform. Which feature can help achieve a high packet rate with lower CPU consumption?___
A. Network I/O Control
B. SplitRX
C. ERSPAN
D. LACP
【单选题】
What is the VMware-recommended best practice for Fibre Channel zoning?___
A. soft zoning
B. single-initiator-multiple-target zoning
C. single-initiator zoning
D. single-initiator-single-target zoning
【单选题】
How can a vSphere administrator ensure that a set of virtual machines run on different hosts in a DRS cluster?___
A. Use a VM-Host affinity rule.
B. Add the VMs to a vApp.
C. Use a VM-VM affinity rule.
D. Place the VMs in different folders.
【单选题】
vCenter Server Appliance Instance can be backed up using which Client Interface?___
A. vSphere Client Interface
B. vSphere Web Client Interface
C. VMware Host Client Interface
D. Virtual Appliance Management Interface
【单选题】
What tool can capture network traffic at the uplinks, or vSwitch, or virtual port levels?___
A. tcpdump-uw
B. wireshark
C. pktcap-uw
D. pcap
【单选题】
Which storage feature always requires the use of third-party software on ESXi?___
A. Hardware Acceleration for NAS devices
B. VVOL
C. Hardware Acceleration for Block
D. evices
【单选题】
An ESXi host's VMCA-Signed certificate has expired. How can the certificate be renewed?___
A. In the vSphere Web Client, browse to the host in question. Click the Manage tab and select settings. Select System and click Certificate, then click the Renew button.
B. In the vSphere Web Client, browse to the host in question. Click the Manage tab and select settings. Select System and click Certificate, then click the Refresh CA Certificates button.
C. Run the command /sbin/generate-certificates on the affected host.
D. Disconnect the host from vCenter Server and reconnect it.
【单选题】
Which is the correct order for upgrading vSphere components?___
A. vCenter Server, ESXi hosts, VMware Tools, Virtual Machine hardware
B. VMware Tools, Virtual Machine hardware, ESXi hosts, vCenter Server
C. vCenter Server, Virtual Machine hardware, VMware tools, ESXi hosts
D. ESXi hosts, vCenter Server, Virtual Machine hardware, VMware Tools
【单选题】
Which iSCSI initiator type can be used with any network interface card?___
A. Software iSCSI initiator
B. Software FCoE adapter
C. Hardware Independent iSCSI initiator
D. Hardware Dependent iSCSI initiator
【单选题】
An administrator is attempting to power on a virtual machine with 32GB of memory. The operation fails with the following error: <Could not power on VM: No space left on device> <Checking the space on the virtual machine's datastore, there is 30GB free.> Which action would allow the VM to power on?___
A. Set a 2GB memory reservation on the VM.
B. Mount the virtual disk from the affected VM on to another virtual machine and free up space from within the OS.
C. Enable vSphere HD admission control on the cluster in which the VM resides.
D. Set a 2GB memory limit on the VM.
推荐试题
【单选题】
夜间巡线应携带足够的___。
A. 干粮
B. 照明用具
C. 急救药品
D. 防身器材
【单选题】
灾害发生后,若需对配电线路、设备进行巡视,应得到___批准。
A. 设备运维管理单位领导
B. 设备运维管理单位
C. 工作负责人
D. 值班调控人员
【单选题】
巡视中发现高压配电线路、设备接地或高压导线、电缆断落地面、悬挂空中时,室内人员应距离故障点___m以外。
A. 2
B. 4
C. 6
D. 8
【单选题】
倒闸操作中发生疑问时,___。待发令人再行许可后,方可继续操作。
A. 不得更改操作票,应立即停止操作,并向发令人报告
B. 应立即停止操作,并向发令人报告
C. 不得更改操作票,应立即停止操作
D. 应立即向发令人报告
【单选题】
停电拉闸操作应按照___的顺序依次进行,送电合闸操作应按与上述相反的顺序进行。禁止带负荷拉合隔离开关(刀闸)。
A. 断路器(开关)—负荷侧隔离开关(刀闸)—电源侧隔离开关(刀闸)
B. 负荷侧隔离开关(刀闸)——断路器(开关)——电源侧隔离开关(刀闸)
C. 断路器(开关)—电源侧隔离开关(刀闸)—负荷侧隔离开关(刀闸)
D. 负荷侧隔离开关(刀闸)——电源侧隔离开关(刀闸)——断路器(开关)
【单选题】
断路器(开关)与隔离开关(刀闸)无机械或电气闭锁装置时,在拉开隔离开关(刀闸)前应___。
A. 确认断路器(开关)操作电源已完全断开
B. 确认断路器(开关)已完全断开
C. 确认断路器(开关)机械指示正常
D. 确认无负荷电流
【单选题】
___时,禁止就地倒闸操作和更换熔丝。
A. 大风
B. 雷电
C. 大雨
D. 大雪
【单选题】
___断路器(开关)前,宜对现场发出提示信号,提醒现场人员远离操作设备。
A. 远方遥控操作
B. 远方程序操作
C. 就地操作
D. 拉开
【单选题】
装设柱上开关(包括柱上断路器、柱上负荷开关)的配电线路停电,应___。送电操作顺序与此相反。
A. 先断开柱上开关,后拉开隔离开关(刀闸)
B. 先拉开隔离开关(刀闸),后断开柱上开关
C. 先停主线开关,后停支线柱上开关
D. 先停支线柱上开关,后停主线开关
【单选题】
配电变压器停电,应___。送电操作顺序与此相反
A. 先拉开高压侧熔断器,后拉开低压侧开关(刀闸)
B. 先拉开低压侧开关(刀闸),后拉开高压侧熔断器
C. 先拉开低压侧分路开关,后拉开低压侧总开关
D. 先拉开低压侧总开关,后拉开低压侧分路开关
【单选题】
摘挂跌落式熔断器的熔管,应使用___,并派人监护。
A. 绝缘棒
B. 验电器
C. 操作杆
D. 专用工具
【单选题】
砍剪靠近带电线路的树木,___应在工作开始前,向全体作业人员说明电力线路有电。
A. 工作负责人
B. 工作许可人
C. 工作票签发人
D. 专业室领导
【单选题】
砍剪靠近带电线路的树木,工作负责人应在工作开始前,向全体作业人员说明电力线路有电;人员、树木、绳索应与导线保持10kV___m的安全距离。
A. 0.7
B. 1.0
C. 1.5
D. 3.0
【单选题】
为防止树木(树枝)倒落在线路上,应使用绝缘绳索将其拉向与线路___的方向,绳索应有足够的长度和强度,以免拉绳的人员被倒落的树木砸伤。
A. 相反
B. 60°
C. 90°
D. 相同
【单选题】
上树时,应使用安全带,安全带不得系在待砍剪树枝的___附近或以上。不得攀抓脆弱和枯死的树枝;不得攀登已经锯过或砍过的未断树木。
A. 茎部
B. 断口
C. 枝丫
D. 根部
【单选题】
使用油锯和电锯的作业,应由___的人员操作。使用时,应先检查所能锯到的范围内有无铁钉等金属物件,以防金属物体飞出伤人。
A. 熟悉工作组人员
B. 熟悉操作方法
C. 熟悉机械性能
D. 熟悉机械性能和操作方法
【单选题】
登杆塔前,应核对___。
A. 杆号
B. 线路名称和杆号
C. 杆基
D. 线路名称
【单选题】
遇有冲刷、起土、上拔或导地线、拉线松动的杆塔,登杆塔前,应先___,打好临时拉线或支好架杆。
A. 培土加固
B. 三交待
C. 两穿一戴
D. 测量接地电阻
【单选题】
攀登杆塔过程中应检查___和金具锈蚀情况。
A. 纵向裂纹
B. 横向裂纹
C. 裂纹
D. 绝缘子污染
【单选题】
在人员密集或有人员通过的地段进行杆塔上作业时,___下方应按坠落半径设围栏或其它保护措施。
A. 杆塔
B. 杆上人员
C. 作业点
D. 横担
【单选题】
作业人员攀登杆塔时,手扶的构件应___。
A. 牢固
B. 方便
C. 灵活
D. 耐用
【单选题】
在杆塔上使用梯子或临时工作平台,应将两端与固定物可靠连接,一般应由___人在其上作业。
A. 一
B. 二
C. 三
D. 四
【单选题】
立、撤杆应设专人统一指挥。开工前,应交待施工方法、指挥信号和___。
A. 安全措施
B. 技术措施
C. 组织措施
D. 应急措施
【单选题】
立、撤杆塔时,禁止基坑内有人。除指挥人及指定人员外,其他人员应在杆塔高度的___倍距离以外。
A. 1.1
B. 1.2
C. 1.3
D. 1.4
【单选题】
使用临时拉线时,一个锚桩上的临时拉线不得超过___。
A. 一根
B. 两根
C. 三根
D. 四根
【单选题】
利用已有杆塔立、撤杆,应检查杆塔___及拉线和杆塔的强度,必要时应增设临时拉线或采取其他补强措施。
A. 基础
B. 根部
C. 中部
D. 上部
【单选题】
使用吊车立、撤杆塔,钢丝绳套应挂在电杆的___以防止电杆突然倾倒。
A. 中间位置
B. 根部
C. 上部
D. 适当位置
【单选题】
使用倒落式抱杆立、撤杆时,主牵引绳、尾绳、杆塔中心及抱杆顶应在一条直线上,抱杆下部应固定牢固,抱杆顶部应设临时拉线,并由___均匀调节控制。
A. 安全监护人
B. 技术人员
C. 工作负责人
D. 有经验的人员
【单选题】
在带电线路、设备附近立、撤杆塔,杆塔、拉线、临时拉线、起重设备、起重绳索应与带电线路、设备保持表6-1所规定的安全距离,且应有防止___接近带电导线的措施。
A. 立杆过程中拉线跳动和杆塔倾斜
B. 立、撤杆过程中拉线跳动和杆塔倾斜
C. 立、撤杆过程中拉线跳动
D. 撤杆过程中拉线杆塔倾斜
【单选题】
在110kV带电设备附近立、撤杆塔,杆塔、拉线、临时拉线、起重设备、起重绳索应与带电线路、设备保持的最小安全距离为___m。
A. 3
B. 4
C. 5
D. 6
【单选题】
在35kV带电设备附近立、撤杆塔,杆塔、拉线、临时拉线、起重设备、起重绳索应与带电设备保持的最小安全距离为___ m。
A. 3
B. 4
C. 5
D. 6
【单选题】
在交叉跨越各种线路、铁路、公路、河流等地方放线、撤线,应先取得有关主管部门同意,做好跨越架搭设、封航、封路、在路口设专人持___看守等安全措施。
A. 信号旗
B. 警示标志
C. 对讲机
D. 荧光棒
【单选题】
交叉跨越各种线路、铁路、公路、河流等放、撤线时,应先取得___同意,做好跨越架搭设、封航、封路、在路口设专人持信号旗看守等安全措施。
A. 主管部门
B. 上级部门
C. 经信部门
D. 交通部门
【单选题】
拆除杆上导线前,应检查___,做好防止倒杆措施,在挖坑前应先绑好拉绳。
A. 卡盘
B. 拉线
C. 埋深
D. 杆根
【单选题】
放线、紧线时,处理有卡、挂现象,应松线后处理。处理时操作人员应站在卡线处___。
A. 内侧
B. 外侧
C. 下方
D. 上方
【单选题】
放线、紧线与撤线时,作业人员不应站在或跨在已受力的牵引绳、导线的___,展放的导线圈内以及牵引绳或架空线的垂直下方。
A. 外角侧
B. 内角侧
C. 上方
D. 受力侧
【单选题】
___采用突然剪断导线的做法松线。
A. 原则上不得
B. 可以
C. 禁止
D. 在保障安全前提下可
【单选题】
架空绝缘导线不得视为___。
A. 绝缘设备
B. 导电设备
C. 承力设备
D. 载流设备
【单选题】
邻近带电导线的工作中,应使用绝缘无极绳索,风力应小于___ 级,并设人监护。
A. 4
B. 5
C. 6
D. 7
【单选题】
在带电杆塔上进行测量、防腐、巡视检查、紧杆塔螺栓、清除杆塔上异物等工作,风力应小于___级。配电《安规》
A. 6
B. 5
C. 4
D. 3