【简答题】
In 1941, Adolf Hitler, leader of Nazi Germany, launched an attack against the Soviet Union, as Russia then was called. Hitler's military might was unequaled. His war machine had mowed down resistance in most of Europe. Hitler expected a short campaign but, like Napoleon before him, was taught a painful lesson. The Russian winter again came to the aid of the Soviet soldiers.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
1941年,纳粹德国元首阿道夫·希特勒进攻当时被称作苏联的俄罗斯。希特勒的军事实力堪称无敌。他的战争机器扫除了欧洲绝大部分地区的抵抗。希特勒希望速战速决,但是,就像在他之前的拿破仑一样,他得到的是痛苦的教训。仍是俄罗斯的冬天助了苏维埃士兵一臂之力。
相关试题
【简答题】
In the spring of 1812, Napoleon assembled an army of six hundred thousand men on the borders of Russia. The soldiers were well trained, efficient, and well equipped. This military force was called the Grand Army. Napoleon, confident of a quick victory, predicted the conquest of Russia in five weeks.
【简答题】
Shortly afterwards, Napoleon's army crossed the Neman River into Russia. The quick, decisive victory that Napoleon expected never happened. To his surprise, the Russians refused to stand and fight. Instead, they retreated eastward, burning their crops and homes as they went. The Grand Army followed, but its advance march soon became bogged down by slow-moving supply lines.
【简答题】
In August, the French and Russian armies engaged at Smolensk, in a battle that left over ten thousand dead on each side. Yet, the Russians were again able to retreat farther into Russian territory. Napoleon had won no decisive victory. He was now faced with a crucial decision. Should he continue to pursue the Russian army? Or should he keep his army in Smolensk for the approaching winter?
【简答题】
Napoleon took the gamble of pressing on to Moscow, 448 kilometers away. On September 7, 1812, the French and Russian armies met in fierce battle at Borodino, 112 kilometers west of Moscow. By nightfall, thirty thousand French and forty-four thousand Russians lay dead or wounded on the battlefield.
【简答题】
Again, the Russian army retreated to safety. Napoleon had a clear path to Moscow, but the occupation of the city became an empty victory. The Russians fled their capital. Soon after the French arrived, a raging fire destroyed two-thirds of the city. Napoleon offered a truce to Alexander I, but the Russian czar knew he could bide his time: "We shall let the Russian winter fight the war for us."
【简答题】
Napoleon soon realized he could not feed, clothe, and quarter his army in Moscow during the winter. In October 1812, he ordered his Grand Army to retreat from Moscow.
【简答题】
The French retreat turned into a nightmare. From fields and forests, the Russians launched hit-and-run attacks on the French. A short distance from Moscow, the temperature had already dropped to minus 4 degrees Celsius. On November 3, the winter's first snow came. Exhausted horses fell dead in their tracks. Cannon became stuck in the snow. Equipment had to be burned for fuel. Soldiers took ill and froze to death. The French soldiers dragged on, leaving the dead along every mile.
【简答题】
As the Russian army was gathering its strength, the French had to flee Russia to avoid certain defeat. At the Berezina River, the Russians nearly trapped the retreating French by burning the bridges over the swollen river. But Napoleon, by a stroke of luck, was able to build two new bridges. Thousands of French soldiers escaped, but at the cost of fifty thousand dead. Once across the Berezina, the tattered survivors limped toward Vilna.
【简答题】
Of the six hundred thousand soldiers Napoleon had led into Russia, less than one hundred thousand came back. The weakened French army continued its retreat westward across Europe. Soon, Britain, Austria, Russia, and Prussia formed a powerful alliance and attacked these stragglers. In March 1814, Paris was captured. Napoleon abdicated and went into exile, his empire at an end.
【简答题】
By early 1941, Adolf Hitler, leader of Nazi Germany, had seized control of most of Europe. To the east of Hitler's German empire was the Soviet Union. On June 22, 1941, without a declaration of war, Hitler began an invasion of the Soviet Union that was the largest military land campaign in history. Confident of a quick victory, Hitler expected the campaign to last no longer than three months. He planned to use the blitzkrieg, or "lightning war," tactics that had defeated the rest of Europe. The invasion had three broad thrusts: against Leningrad and Moscow and through the Ukraine.
【简答题】
Caught off guard by the invasion, Soviet leader Joseph Stalin instructed the Russian people to "scorch the earth" in front of the German invaders. Farms and factories were burned, destroyed, or rendered useless. During the first ten weeks of the invasion, the Germans pushed the front eastward, and the Russians suffered more than a million casualties.
【简答题】
In the north, the Germans closed in on Leningrad. Despite great suffering, however, the people of Leningrad refused to surrender. As the battle of Leningrad dragged on into winter, the city's situation became desperate. As food ran out, people died from hunger and disease. By the middle of the winter of 1941-1942, nearly four thousand people starved to death every day. Close to one million people died as a result of the siege.
【简答题】
In the center of Russia, Hitler's goal was the capture of Moscow. Because the Germans had anticipated a quick victory, they had made no plans for winter supplies. October arrived with heavy rains. "General Mud" slowed down the movement of the Germans' lightning attack.
【简答题】
As Hitler's armies drew closer and closer to Moscow, an early, severe winter settled over the Soviet Union, the harshest in years. Temperatures dropped to minus 48 degrees Celsius. Heavy snows fell. The German soldiers, completely unprepared for the Russian winter, froze in their light summer uniforms. The German tanks lay buried in the heavy snowbanks. The Russian winter brought the German offensive to a halt.
【简答题】
By the summer of 1942, Hitler had launched two new offensives. In the south, the Germans captured Sevastopol. Hitler then pushed east to Stalingrad, a great industrial city that stretched for 48 kilometers along the Volga River. Despite great suffering, Soviet defenders refused to give up Stalingrad.
【简答题】
In November 1942, the Russians launched a counterattack. With little or no shelter from the winter cold in and around Stalingrad, German troops were further weakened by a lack of food and supplies. Not until January 1943 did the Germans give up their siege. Of the three hundred thousand Germans attacking Stalingrad, only ninety thousand starving soldiers were left. The loss of the battle for Stalingrad finally turned the tide against Hitler. The German victories were over, thanks in part to the Russian winter.
【简答题】
During 1943 and 1944, the Soviet armies pushed the German front back toward the west. In the north, the Red Army broke the three-year siege of Leningrad with a surprise attack on January 15, 1944. Within two weeks, the heroic survivors of Leningrad saw their invaders depart. By March 1944, the Ukraine farming region was again in Soviet hands. On May 9, 1944, Sevastopol was liberated from the Germans. The Russians were now heading for Berlin.
【简答题】
For Hitler, the invasion of the Soviet Union had turned into a military disaster. For the Russian people, it brought unspeakable suffering. The total Soviet dead in World War II reached almost 23 million.
【简答题】
The elements of nature must be reckoned with in any military campaign. Napoleon and Hitler both underestimated the severity of the Russian winter. Snow, ice, and freezing temperatures took their toll on both invading armies. For the Russian people, the winter was an icy defender.
【单选题】
________不属于鼠类及体表寄生虫携带的病原体。___
A. 鼠疫耶尔森菌
B. 汉坦病毒
C. 黄病毒属病毒
D. 致病性钩端螺旋体
【单选题】
病媒生物死体样本运送,如果在24h内不能到达实验室的,运送过程中箱内温度应保持在_____。___
A. 4℃以下
B. 0℃以下
C. -20℃以下
D. 4℃以上
【单选题】
病媒生物死体样本运送,如果在装箱后4h内能够到达实验室的,运送过程中箱内温度应保持在______。___
A. 4℃以下
B. 0℃以下
C. -20℃以下
D. 4℃以上
【单选题】
病媒生物的死体样本运送,如果4h-24h内能到达实验室的,应将样品置于-30℃冷冻后再送样,运送过程中箱内温度应保持在________。___
A. 4℃以下
B. 0℃以下
C. -20℃以下
D. 4℃以上
【单选题】
恰加斯病也称为美洲锥虫病,其重要的传播媒介是________。___
A. 采采蝇
B. 厩螫蝇
C. 锥蝽
D. 埃及伊蚊
【单选题】
_______是黑热病内脏利什曼病的主要传播媒介。___
【单选题】
对于用作虫媒病毒分离或检测的蚊类标本,现场采集后应采用_______方式处置和运送。___
A. 杀虫剂熏杀+常温运输
B. 等蚊虫自然死亡+常温运输
C. 冷冻处死+常温运输
D. 冷冻处死+冷冻状态运输
【单选题】
_______不适用于入出境集装箱携带蝇、蚊、蠓的采集。___
A. 挥网法
B. 电动吸蚊器法
C. 直接捡取法
D. 二氧化碳诱蚊灯法
【单选题】
入境航空器应在______开始病媒生物监测。___
A. 卸货完成后
B. 抵达后
C. 等航空公司通知
D. 发现病媒生物时
【单选题】
进行集装箱携带输入性病媒生物监测时应准备的个人防护用品包括______。___
A. 乳胶手套、防护服
B. 防毒面具
C. 自给式呼吸器
D. 化学防护服
【单选题】
若要对采集到的输入性鼠类进行携带的病毒进行检测,取得其内脏器官的保存温度是_____。___
A. -80℃或以下
B. 0℃
C. 常温
D. 4℃-8℃
【单选题】
截获输入性活鼠或来自鼠疫流行区死鼠及经总署专家组确认和复核属于全国口岸首次截获的病媒生物应在______报告总署。___
A. 2小时之内
B. 8小时之内
C. 12小时之内
D. 24小时之内
【单选题】
入境船舶的蚊类和蝇类等双翅目病媒生物监测调查应白天在检疫锚地停泊期间进行,锚位距陆地距离不少于______,或在船舶靠泊后_____内进行。___
A. 1000 m;1h
B. 800 m、2 h
C. 400 m、4 h
D. 100 m、24 h
【单选题】
开展入境船舶输入性病媒生物监测工作中,在采集并保存病媒生物时由________陪同人员确认。___
A. 旅行社
B. 船方
C. 代理公司
D. 海事部门
【单选题】
在国境口岸或者交通工具上发现______有反常死亡或者死因不明的,国境口岸有关单位或者交通工具的负责人,必须立即向卫生检疫机关报告,迅速查明原因,实施卫生处理。___
【单选题】
采用鼠夹法监测鼠密度,应连续布放______。___
【单选题】
______不属于口岸区域鼠类常用监测方法。___
A. 鼠笼法
B. 鼠夹法
C. 目测法
D. 粉迹法
【单选题】
采用粉迹法监测鼠类密度时,滑石粉块的尺寸是______。___
A. 20cm×20cm
B. 30cm×30cm
C. 40cm×40cm
D. 50cm×50cm
【单选题】
______不属于蚊虫幼虫监测指标。___
A. 容器指数
B. 刺叮指数
C. 房屋指数
D. 布雷图指数
【单选题】
______不属于蚊虫成虫监测方法。___
A. 人帐诱法
B. 人工小时法
C. 小黑板法
D. 诱蚊器收集法
【单选题】
______不属于蝇类成虫监测方法。___
A. 诱蝇笼诱捕法
B. 捕蝇网网捕法
C. 直接目测法
D. 路径指数法
推荐试题
【单选题】
BXA23.在项目的风险评估会议上,观察清单中的一个风险项发生概率急剧增加。项目经理应首先更新哪一项内容?___
A. 风险管理计划
B. 风险登记册
C. 假设日志
D. 风险应对计划
【单选题】
BXA24.在项目启动大会之后,分配给项目团队的一位技术专家对被选中参与项目工作表示不满,他的态度对其他团队成员造成负面影响。项目经理应该怎么做?___
A. 需要人力资源部门替换该技术专家
B. 尝试了解该技术专家态度的原因,然后根据收集的信息采取进一步的行动
C. 向该技术专家发出书面警告,指明不当行为是不可容忍的
D. 向该技术专家分配避免与其他团队成员互动的任务
【单选题】
BXA25.—些之前未识别到的相关方报告说,他们的职能领域受到很大影响,但没有持续通知他们关键项目的状态。项目经理首先应该做什么?___
A. 审查项目的沟通方法
B. 检查并更新相关方登记册
C. 确定沟通项目状态的新策略
D. 邀请所有相关方参加状态会议
【单选题】
BXA26.—个关键项目落后于进度,并超出预算。项目管理办公室(PMO)的详细分析透露,并非所有关键人员都被识别,并且没有积极的过程来接洽和管理这些人员。项目经理应该采取什么纠正措施?___
A. 改进相关方参与计划
B. 查看权力/利益方格
C. 控制相关方参与程度
D. 更新沟通管理计划
【单选题】
BXA27.—个项目涉及位于全球各地的团队成员,产生了许多不同意见。新项目经理通过成功促进团队协作和问题解决提高生产力。项目经理使用的是什么工具和技术?___
A. 冲突管理
B. 沟通模型
C. 群体决策技术
D. 虚拟团队
【单选题】
BXA28.—个项目已经分包给破产的供应商,项目经理遵循批准的行动,但是一名项目相关方质疑该行动是否恰当。项目经理应该向该项目相关方分享什么文件?___
A. 风险登记册
B. 风险紧迫性评估
C. 影响分析
D. 定性分析
【单选题】
BXA29.公司的新产品系列将在两个月内发布,95%的项目任务均已完成。但是,管理层却决定终止产品发布并取消项目。项目经理下一步该怎么做?___
A. 立即停止所有项目任务
B. 按原计划完成项目
C. 释放资源并记录项目状态
D. 收尾项目并更新经验教训
【单选题】
BXA30.基于不断变化的立法,项目团队识别到大量额外的需求,项目经理要求团队针对每个需求提交变更请求。项目经理下一步应该怎么做?___
A. 变更范围和基准
B. 审查变更管理计划,并按该计划执行
C. 安排召开变更控制委员会(CCB)会议,加快批准
D. 向发起人提交时间和成本偏差请求
【单选题】
BXA31.—家公司计划推出一个新的数字银行解决方案。在项目启动时,识别到一个关键依赖关系,需要在产品推出前获得监管部门的批准。这被添加到风险登记册,并由项目经理积极监控。目前,仍未得到监管部门的批准,这可能会导致产品推出延期。项目经理如何能够减轻该风险?___
A. 准备风险应对措施
B. 在风险登记册中更新并跟踪该风险
C. 调整项目进度计划,包含应急应对措施
D. 评估被监管拒绝的可能性
【单选题】
BXA32.客户希望增加股东权益的总和,提高其在全球市场的品牌知名度。客户的主要目标是什么?___
A. 为组织战略改善整体业务支持
B. 增加营销预算
C. 提高商业价值
D. 通过重新投资其他业务组合提高市场份额
【单选题】
BXA33.客户需要批准的产品指南,以便在新的站点实施己完成的项目解决方案。但是,客户却无法实施解决方案,因为可交付成果不能按照已批准需求的规范执行。若要避免这个问题,项目经理应该事先做什么?___
A. 完成统计抽样分析
B. 应用质量检查
C. 执行质量审计
D. 核实变更
【单选题】
BXA34.—名新成员加入团队,该团队的报告结构发生多次变更。若要快速使这位新团队成员适应,项目经理应该查阅哪一份文件?___
A. 项目组织图
B. 层级资源图
C. 责任分配矩阵(RAM)
D. 资源管理计划
【单选题】
BXA35.某个新项目将使用特定软件发布。在项目启动大会上,一名团队成员记起在之前的一个项目他们已经使用了该软件工具的第一版,但该软件造成许多问题。该项目经理接下来应该怎么做?___
A. 项目团队成员解释说,自上一个项目后,技术已经发生了很大变化,以后不会发生问题
B. 查看过往项目的经验教训说明,识别新项目中的类似风险
C. 立即将潜在风险上报给项目发起人,以便能够获得额外的资金
D. 结束项目并收集经验教训,让未来的项目可以从该经验教训中获益
【单选题】
BXA36.某项目出现跨项目资源使用问题及高层面临变更风险,项目经理应该采用哪种风险应对方法?___
【单选题】
BXA37.批准项目章程之后,人力资源总监要求增加项目范围。一名项目团队成员在没有通知项目经理的情况下增加了这些范围。项目经理应该怎么做?___
A. 与该团队成员讨论该问题
B. 执行实施整体变更控制过程
C. 寻求项目发起人的指导
D. 与项目管理办公室(PMO)一起审查范围变更
【单选题】
BXA38.虽然前两个可交付成果是完整的,但由于财务原因,项目被取消。项目经理应该做?___
A. 向管理层解释项目应该继续下去
B. 迅速进入收尾阶段
C. 进行资源遣散
D. 内部分析原因,并提交相关的建议
【单选题】
BXA39.为解决具有挑战性的客户请求,启动了一个项目。该项目必须在短时间内交付。项目经理应该怎么做来尽可能提高项目的成功率?___
A. 安排采购会议,加快采购
B. 将问题上报给项目发起人
C. 开始执行项目活动
D. 与团队一起制定详细计划
【单选题】
BXA40.项目的进度很紧张,延迟交付不可接受。职能经理要求将一名资源调至优先级更高的项目,但是,该团队成员正在从事一个关键路径活动。若要避免对项目的负面影响,项目经理应该怎么做?___
A. 请求项目发起人确保提供另一名资源
B. 与职能经理讨论该情形
C. 修改进度计划以使用浮动时间
D. 使用资源平衡
【单选题】
BXA41.项目经理面对一个由两个合资企业组成的指导委员会,他们拥有对立的优先级。一个伙伴希望加快进度;而第二个合作伙伴想要高质量,并且愿意接受更长时间的进度。若要解决这个冲突,项目经理应该怎么做?___
A. 将该冲突作为一项风险纳入风险管理计划中
B. 更新问题日志并监督该冲突的解决方案
C. 启动一个新的范围定义,并与所有项目相关方进行协商
D. 将该问题包含在质量管理计划中
【单选题】
BXA42.项目经理负责管理一个项目,该项目正处于规划阶段。项目经理必须快速识别哪些项目相关方需要最多关注。项目经理可以从哪里找到这个信息?___
A. 相关方参与计划
B. 相关方登记册
C. 执行、负责、咨询和知情(RACI)矩阵
D. 问题日志
【单选题】
BXA43.项目即将完成一个重要阶段,项目经理正在获得资源开始下一个阶段,在准备阶段收尾时,项目经理评审了绩效测量指标,发现不明原因的变化。项目经理应该怎么做?___
A. 检查之前项目的知识库
B. 在经验教训会上进行因果分析
C. 在团队会议上评审测量指标
D. 将工作分解结构(WBS)与实际可交付成果对比
【单选题】
BXA44.项目经理从一个符合进度和预算的项目中辞职。在聘用替代的新项目经理后,团队反对新项目经理提出的意见。团队处于下列哪一个发展阶段?___
A. 形成
B. 规范
C. 成熟阶段
D. 震荡阶段
【单选题】
BXA45.项目经理得知一款软件可以提高当前和未来项目任务的效率,由于这款软件对公司来说是新软件,工程师不熟悉该软件。项目经理决定派遣最高级别工程师参加外部培训课程。项目经理采用了何种风险策略?___
【单选题】
BXA46.项目经理定义项目范围后,团队成员对项目需求表示不满。他们要求审查范围说明书来分析风险,并进一步澄清范围。项目经理应该怎么做?___
A. 忽略该请求,并指示团队保持己定义的范围
B. 与团队成员召开引导式研讨会
C. 要求团队成员创建一份亲和图
D. 要求团队成员召开头脑风暴会议
【单选题】
BXA47.项目经理发现公司的质量保证(QA)部门可能没有足够的人员根据合同约定的进度计划测试项目产品。项目经理首先应该怎么做?___
A. 审查问题日志
B. 更新风险登记册
C. 取消一些非关键测试
D. 压缩进度计划
【单选题】
BXA48.项目经理负责安装和调试一个新的生产设施。一条新的生产线已准备好调试,且正在进行试生产。若要确保生产线的运行符合技术规范,项目经理应使用什么工具或技术?___
A. 标杆对照
B. 控制图
C. 检查
D. 流程图
【单选题】
BXA49.项目经理负责管理一个项目,该项目将实施一项新技术。若要识别与项目相关的风险,项目经理可以使用如下各项作为工具,除了___
A. 头脑风暴
B. 项目管理计划
C. 专家判断
D. 引导
【单选题】
BXA50.项目经理负责管理一个正在进行的项目,该项目存在质量问题。团队成员认为质量保证对项目没有增加任何价值。此时项目经理应该怎么做?___
A. 修订项目管理计划
B. 修订质量管理计划
C. 执行根本原因分析
D. 控制质量测量指标
【单选题】
BXA51.项目经理观察到项目团队成员在项目开始时感觉没什么信心。在项目启动会议(Kick-OffMeeting)上,项目经理与团队成员进行头脑风暴的好处是:___
A. 让消极者离开
B. 为团队成员灌输信心
C. 从一开始就识别风险
D. 帮助沟通
【单选题】
BXA52.项目经理加入一个项目,但项目团队缺乏必要的技能,来产生一个关键可交付成果。项目经理应该怎么做?___
A. 将该可交付成果分配给一名拥有学习新技能能力的团队成员
B. 与项目发起人协商,聘请拥有必要技能的外部资源
C. 终止执行项目,直到必要的资源出现
D. 将培训作为项目管理计划中项目工作的组成部分
【单选题】
BXA53.项目经理加入一个设计阶段接近完成的项目。虽然客户已经批准所有设计图纸,但项目经理发现包含在最终设计中的多项客户变更。这些变更尚未经过审核和批准。项目经理下一步应该怎么做?___
A. 让客户提交变更请求记录这些变更
B. 提交CCB进行变更审批
C. 与相关方修改变更管理流程
D. 停止所有工作,减轻这些变更对成本、时间和质量的影响
【单选题】
BXA54.项目经理完成了一个新产品开发项目的规划过程。在继续进入执行过程组之前需要完成的最后一个重要里程碑是什么?___
A. 最终确定项目章程
B. 接收执行项目的项目资金
C. 获得发起人和相关方的批准
D. 执行相关方管理策略
【单选题】
BXA55.项目经理需要从不同职能经理那里招募团队成员。项目经理应使用什么?___
A. 资源日历
B. 协商
C. 募集
D. 技能图
【单选题】
BXA56.项目经理需要快速批准项目计划,为了估算获得批准所需的时间,项目经理必须决定哪些批准人可能需要特别注意。下面哪一项将帮助项目经理决定这个问题?___
A. 检查绩效报告
B. 执行相关方分析
C. 应用分析技术
D. 参与观察和对话
【单选题】
BXA57.项目经理应该使用哪一项工具或技术来执行定性风险分析?___
A. 概率分布
B. 决策树分析
C. 概率和影响矩阵
D. 成本风险模拟
【单选题】
BXA58.项目经理应在哪里存档所有相关项目文件和经验教训?___
A. 工作授权系统
B. 项目管理信息系统(PMIS)
C. 项目数据管理系统
D. 配置管理系统
【单选题】
BXA59.项目经理在管理客户期望以及指导实现项目目标方面有困难。若要解决这些问题,项目经理应将客户的高层次需求记录在哪里?___
A. 项目章程
B. 工作分解结构(WBS)
C. 需求管理计划
D. 相关方管理计划
【单选题】
BXA60.项目经理召开团队研讨会,讨论质量管理计划。三名团队成员认为质量保证无法为项目增值。项目经理应该怎么做?___
A. 将这些团队成员介绍给发起人进行澄清
B. 评估质量保证的绩效
C. 提醒这些团队成员,执行质量保证可以降低项目成本
D. 派这些团队成员参加质量管理培训
【单选题】
BXA61.项目经理正与一名承认未使用章程的同事讨论项目章程。为了向同事说明项目章程的重要性,项目经理表明项目章程很重要,因为项目章程的批准即意味着下列哪一项?___
A. 启动阶段可以开始
B. 执行阶段正式开始
C. 详细需求清单的正式批准
D. 项目的正式授权
【单选题】
BXA62.项目经理正在实施一个预算紧张的项目,为确保项目成功,项目经理在制定项目章程时应使用什么?___
A. 经验教训
B. 质量测量指标
C. 战略计划
D. 成本基准