【多选题】
Which two statements about vCenter HA are correct? (Choose two.)___
A. ESXi 5.5 or later is required.
B. vCenter HA network latency between nodes must be less than 50 ms.
C. NFS datastore is supported.
D. It must be deployed on a 3
E. SXi host cluster with DRS enabled.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
相关试题
【多选题】
An attempt to delete NFS datastore from a ESXi host returns the error: Sysinfo error on operation returned the following status:< Busy> Which two statements could explain this failure? (Choose two.)___
A. NFS datastore is a part of Storage DRS Cluster.
B. NFS.VolumeRemountFrequency value is set to 30.
C. Storage I/O Control is enabled on NFS datastore.
D. NFS datastore has running or registered virtual machines.
【多选题】
An administrator finds that the Microsoft Exchange virtual machines are exhibiting network latency. What two in-guest changes can help decrease latency? (Choose two.)___
A. LRO
B. TSO
C. SR-IOV
D. PVRDMA
【多选题】
Which two types of iSCSI adapters require VMkernel networking configuration? (Choose two.)___
A. dependent hardware
B. in-guest
C. software
D. independent hardware
【多选题】
Which two statements are true for NFS v4.1 firewall behavior? (Choose two.)___
A. It closes port 2049.
B. It sets allowed. All flag to TRUE.
C. It sets allowed. All flag to FALSE.
D. It opens port 2049.
【多选题】
A vSphere Administrator attempts to enable Fault Tolerance for a virtual machine but receives the following error: Secondary VM could not be powered on as there are no compatible hosts that can accommodate it. What two options could cause this error? (Choose two.)___
A. The other ESXi host(s) are in Maintenance Mode.
B. Hardware virtualization is not enabled on the other ESXi host(s).
C. The other ESXi host(s) are in Quarantine Mode.
D. Hardware MMU is enabled on the other
E. SXi host(s).
【多选题】
Storage capabilities be populated in what two ways? (Choose two.)___
A. The administrator can use tags to describe capabilities.
B. Default capabilities are provided by vCenter Server.
C. Datastores can advertise their capabilities through VAAI.
D. Datastores can advertise their capabilities through VASA.
【多选题】
In network troubleshooting it is important to know what upstream switch the ESXi host is connected to. Which two features does ESXi provide to help identify the upstream switch? (Choose two.)___
A. Promiscuous mode
B. DPM
C. LLDP
D. CDP
【多选题】
Virtual Volumes supports which three VMware features? (Choose three.)___
A. Instant Clones
B. Distributed Resource Scheduler
C. Linked Clones
D. vMotion
E. Storage Distributed Resource Scheduler
【多选题】
vSphere DRS helps to balance virtual machines with available resources in a vSphere cluster. What three types of resources can be taken into account for balancing? (Choose three.)___
A. CPU
B. physical NIC saturation of an ESXi host
C. virtual NIC saturation of a virtual machine
D. RAM
E. storage latency
【多选题】
Which three design requirements must be satisfied to enable RAID-6 objects in a VMware vSAN cluster? (Choose three.)___
A. vSAN Advanced license or higher
B. vSAN stretched cluster
C. at least six hosts contributing storage
D. deduplication and compression
E. all flash configuration
【多选题】
When using "Cluster resource percentage" for host failover capacity in vSphere HA Admission Control, the total resource requirements are calculated from which two values? (Choose two.)___
A. Total vCPUs assigned to each VM.
B. Average CPU usage on each VM over time.
C. Memory reservations on each VM.
D. Total memory assigned to each VM.
E. Average active memory on each VM over time.
F. CPU reservations on each VM.
【多选题】
Which are four attributes of the Active vCenter HA node? (Choose four)___
A. It uses the vCenter HA network to communicate with the Witness node.
B. It constantly replicates vPostgres data with the Witness node.
C. It uses a public IP address for the management interface.
D. It runs the active vCenter Server Appliance instance.
E. It uses the vCenter HA network for replication of data to the Passive node.
F. It provides a quorum to protect against split-brain situations.
【多选题】
Which are two vCenter Server two-factor authentication methods? (Choose two.)___
A. RSA SecurID
B. Smart Card
C. SAML
D. Symantec VIP
【多选题】
An administrator is creating VMkernel adapters on an ESXi 6.5 host and wants to create separate VMkernel adapters for every type of traffic in the default TCP/IP stack. Which three types of traffic can be explicitly enabled on a separate VMkernel adapter? (Choose three.)___
A. Virtual SAN traffic
B. NFS traffic
C. vMotion traffic
D. vSphere HA traffic
E. Fault Tolerance logging traffic
【多选题】
When migrating a Windows vCenter Server 6.0 to the vCenter Server Appliance 6.5, which two will be migrated by default? (Choose two.)___
A. Local Windows OS users and groups
B. Configuration
C. Custom ports
D. FQDN
E. Historical and Performance data
【多选题】
Which three types of Content Libraries exist within vSphere 6.5? (Choose three.)___
A. Remote Content Library
B. Published Content Library
C. Local Content Library
D. Shared Content Library
E. Subscribed Content Library
【多选题】
An administrator cannot enable multi-processor Fault Tolerance (SMP-FT) for a virtual machine. Which are two possible causes for this? (Choose two.)___
A. The virtual machine is running on a vSAN datastore.
B. The Fault Tolerance network is using a 10Gbit uplink.
C. The virtual machine has 6 vCPUs assigned.
D. The virtual machine has a 1TB VMDK attached.
E. The virtual machine has snapshots present.
【多选题】
Which two statements are true for Predictive DRS? (Choose two.)___
A. It balances resource utilization for virtual machines with unpredictable utilization patterns.
B. It integrates DRS with vRealize Operations Manager to balance workloads for virtual machines before resource utilization spikes occur.
C. It balances resource utilization based on a threshold's algorithm that runs each night.
D. It determines the best placement and balance of virtual machines based on a threshold's algorithm that runs each night in vCenter Server 6.5 Database.
【多选题】
Which two situations could cause a virtual machine to appear with (orphaned) appended to its name? (Choose two.)___
A. if a host failover is unsuccessful
B. if a virtual machine was removed from vCenter Server's inventory
C. if a virtual machine was deployed from template, and the template has been deleted
D. if a virtual machine is unregistered directly on the host
【多选题】
Which three requirements are needed to apply RAID 5 or RAID 6 erasure coding on a vSAN 6.2 or 6.5 object? (Choose three.)___
A. on Disk Format 3.0
B. Hybrid vSAN
C. All Flash vSAN
D. vSAN Advanced License
E. Stretched Cluster Configurations
【多选题】
An administrator sees the following error in the log files: Which two events could be the source of the error message? (Choose two.)___
A. vCenter Server failure
B. VXLAN failure
C. Disk array failure
D. Network failure
E. ESXi host failure
【多选题】
An administrator is attempting to access an ESXi host via the DCUI but is unable to do so. Which could be two possible causes? (Choose two.)___
A. The host in Qhas no out-of-band management capability (i.e. iLO/iDRAC).
B. The SSH service is disabled on the host.
C. Strict lockdown mode is enabled on the host.
D. Normal lockdown mode is enabled and the administrator is a member of the
E. xception User list.
【多选题】
Which two permissions are required to migrate a virtual machine with Storage vMotion? (Choose two.)___
A. Network > Move Network
B. Virtual Machine > Inventory > Move
C. Resource > Migrate powered on virtual machine
D. Datastore > Allocate Space
【多选题】
Which are three supported storage requirements for vCenter Server HA? (Choose three.)___
A. NFS
B. RDM
C. vSAN
D. VMFS
E. JBOD
【多选题】
Which are the two network requirements for a VMware vSAN 6.5 cluster? (Choose two.)___
A. Multicast must be enabled on the physical switches and routers that handle vSAN traffic.
B. vSAN requires IPv6 only.
C. All hosts must have a dedicated 40GbE NIC.
D. The vSAN network supported IPv4 or IPv6.
E. vSAN requires IPv4 only.
【多选题】
Which three prerequisites must be in place prior to enabling secure boot for a virtual machine? (Choose three.)___
A. VirtualMachine.Config.Settings privileges
B. an encrypted USB drive
C. Virtual Hardware version 13 or later
D. Virtual Hardware version 12 or later
E. EFI firmware
【多选题】
A user is given the "Virtual machine user (sample)" role in a vSphere 6.x environment. Which three permissions would the user be able to perform? (Choose three.)___
A. Reset a virtual machine.
B. Power on a virtual machine.
C. Move a host into a cluster.
D. Configure CD media.
E. Migrate a virtual machine with Storage vMotion.
【多选题】
Which three are supported upgrade processes for ESXi host? (Choose three.)___
A. using vSphere Auto Deploy
B. using a TFTP server
C. using Update Manager
D. using an
E. SXCLI command
【多选题】
When enabling Storage DRS on a datastore cluster, which three components are enabled as a result? (Choose three.)___
A. Space load balancing among datastore within the datastore cluster.
B. Initial placement for virtual disks based on space and I/O workload.
C. I/O load balancing among datastores within the datastore cluster.
D. Queue Depth alerting on disks within the datastore cluster.
E. Data de-duplication within the datastore cluster.
【多选题】
What are two features introduced in Network I/O Control version 3? (Choose two.)___
A. Bandwidth reservation per traffic type
B. Network resource pools
C. CoS tagging
D. Bandwidth guarantee to virtual machines
【多选题】
Which two correct virtual machine advanced configuration parameters will accomplish this? (Choose two.)___
A. isolation.device.edit.disable = “FALSE”
B. isolation.device.edit.disable = “TRUE”
C. isolation.device.connectable.disable = “FALSE”
D. isolation.device.connectable.disable = “TRUE”
【多选题】
Which three statements are correct regarding booting an ESXi Host from Fibre Channel SAN? (Choose three.)___
A. Direct connect topology is supported.
B. Each host must have its own boot LUN.
C. ESXi hosts do not require local storage.
D. Multipathing to a boot LUN on an active-passive array is supported.
E. Hosts can share one common boot LUN.
【多选题】
Which two tasks should a vSphere administrator perform if the vmkernel log reports VMFS metadata errors? (Choose two.)___
A. contact VMware technical support
B. reformat the datastore
C. check the device with VOMA
D. ignore the messages
【多选题】
Which two statements are true for a vCenterServer user account that is used for vSphere Data Protection (VDP)? (Choose two.)___
A. The user account must be assigned with Administrator role.
B. The password for the user account cannot contain spaces.
C. The user account should be created in the Single Sign-On domain
D. The user account cannot inherit required permissions from a group role.
【多选题】
Which three storage protocols are supported by Virtual Volumes? (Choose three.)___
A. FCIP
B. FCoE
C. iSCSI
D. NFS v3
E. NFS v4
【多选题】
A vSphere administrator observes a CPU spike on one of the web servers (view the Exhibit.) Which two statements can describe the cause of this activity? (Choose two.)___
A. The network packet size is too large.
B. VMware Tools is not installed.
C. Disk latency is present on the datastore.
D. The network packet size is too small.
【多选题】
Which three operations can cause VMFS metadata updates? (Choose three.)___
A. Restarting a VM using the guest OS.
B. Launching a VM console.
C. Migrating a VM with vMotion.
D. Powering a VM on or off.
E. Expanding a VMFS datastore.
【多选题】
*What two services run on all nodes in a vCenter Server HA cluster? (Choose two.)___
A. vmware-vmon
B. vmware-vpostgres
C. vmare-rbd-watchdog
D. vmware-vcha
【多选题】
Which two statements are true regarding Auto Deploy in version 6.5? (Choose two.)___
A. Auto Deploy can be configured and managed via PowerCLI.
B. Auto Deploy can be configured and managed via the vSphere Client.
C. Auto
D. eploy can be configured and managed via the vSphere Web Client.
【多选题】
What three options can improve network performance for a virtual machine? (Choose three.)___
A. MLD
B. TSO
C. NetFlow
D. LRO
E. SR-IOV
推荐试题
【单选题】
CCD91、一个项目要求从外部供应商购买一些服务器。标准程序要求在做出采购决策前需考虑三个供应商的报价。项目经理应该怎么做?___
A. 发出投标邀请书(IFB)。
B. 准备建议邀请书(RFP)。
C. 提交采购订单(PO)。
D. 发出洽谈邀请。
【单选题】
CCD92、在经验教训会议上,团队的反馈非常积极,项目经理意识到这是团队不想损失可能获得的机会。若想获得团队的诚实反馈,项目经理应该怎么做?___
A. 进行匿名电子调查
B. 使用分析技术收集绩效和其他指标
C. 让发起人参与获得独立评估
D. 正规团队成员的明显偏差
【单选题】
CCD93、一个项目正在实施将为组织提供竞争优势的技术。项目经理了解到,一项刚推出的新技术可能导致计划推出的技术过时。项目经理应该怎么做?___
A. 忽略这技术的发展,并关注项目的原始范围
B. 建议使用新技术来跟上最新的技术发展
C. 执行成本效益分析,以确定升级是否合理
D. 完成影响评估并为项目建议最佳可选方案
【单选题】
CCD94、公司聘请一名项目经理来管理一个小型高端项目,如果这个项目成功,将会为公司带来额外的合作。有效的收尾过程是项目成功的关键因素。为确保成功,项目经理必须产生什么可交付成果?___
A. 验收文件
B. 储备分析
C. 进度报告
D. 采购审计
【单选题】
CCD95、为获得新项目所需的资源,项目经理必须得到所有职能经理的许可,这家公司的组织结构是什么?___
A. 平衡矩阵型组织
B. 弱矩阵型组织
C. 强矩阵型组织
D. 职能型组织
【单选题】
CCD96、一名新的关键相关方担心项目经理没有进行项目进度的重要更新,为了预防这个问题,项目经理应该事先遵循什么?___
A. 相关方沟通需求
B. 沟通管理计划
C. 工作绩效报告
D. 项目沟通
【单选题】
CCD97、由于对项目无关事项的多次讨论和激烈争论。在项目启动大会上,项目经理无法解决所有事项。若要满足所有会议目标,项目经理事先应该做什么?___
A. 仅邀请关键项目相关方
B. 计划更少的会议议程事项
C. 邀请主题专家(SME)
D. 制定基本规则
【单选题】
CCD98、批准项目章程之后,人力资源总监要求增加项目范围,一名项目团队成员在没有获得批准的情况下增加了这些范围。项目经理应该怎么做?___
A. 与该团队成员讨论该问题
B. 执行实施整体变更控制过程
C. 寻求项目发起人的指导
D. 与项目管理办公室(PMO)一起审查范围变更
【单选题】
CCD99、市场营销总监和项目经理开会概括了今年的营销目标,以及为了实现这些目标需要完成的项目。这些要求项目经理确保项目按指示交付。为了获得批准,项目经理下一步应该怎么做?___
A. 将项目经理计划提交给发起人
B. 参与制定项目章程
C. 定义项目范围说明书
D. 定义项目需求
【单选题】
CCD100、在准备演示项目管理计划时,一些部门经理对该计划的方向和范围表示不确定,项目经理应该怎么做?___
A. 变更项目风险登记册并确保项目按计划进行
B. 执行相关方分析以获得对该计划的共识
C. 寻求项目发起人对批准项目计划的支持
D. 提出变更请求,更新项目范围,以满足相关方的期望
【单选题】
CCD101、客户识别到一个新实践产品的性能问题,项目经理应使用哪一个质量成本(COQ)类别来估算这项成本?___
A. 预防成本
B. 外部失败成本
C. 评估成本
D. 内部失败成本
【单选题】
CCD102、一个项目中途,发起人想要改变交付进度计划,项目经理下一步应该怎么做?___
A. 确定这对项目关键路径的影响
B. 将其添加到问题日志中
C. 提出一项变更请求
D. 使用进度压缩技术
【单选题】
CCD103、一个计算机更换项目延迟了两周时间,因为团队发现一些组件存在质量问题,项目经理应该怎么做?___
A. 提交变更请求
B. 重定项目进度计划
C. 更新项目管理计划
D. 取消项目
【单选题】
CCD104、对于由不同国家消费资源提交的可交付成果,项目经理识别到一些质量问题,确定这些问题来自于某国所使用的材料质量。项目经理下一步应该怎么做?___
A. 审查项目的质量标准
B. 通知客户
C. 将问题升级上报给高级管理层
D. 要求资源使用质量更好的原材料
【单选题】
CCD105、项目经理正在实施一个预算紧张的项目,为确保项目成功,项目经理在制定项目章程时应采用什么?___
A. 经验教训
B. 质量测量指标
C. 战略计划
D. 成本基准
【单选题】
CCD106、项目经理在项目中途发现,一个环境机构的新主任担心该项目可能会对环境造成严重影响,并且该主任正在影响项目发起人。项目经理下一步应该怎么做?___
A. 将该主任添加到相关方登记册中
B. 要求项目发起人预告与该主任之间的互动
C. 继续执行项目
D. 停止工作,直到主任担心的问题解决
【单选题】
CCD107、一个项目团队正在不同时区工作,团队成员之间经常出现误解,尽管项目经理试图解决这个问题,但这个问题一直没有得到解决。若要改善这种情况,项目经理应该怎么做?___
A. 在团队会议上解决这个问题
B. 与每位团队成员分别解决这个问题
C. 修订沟通管理计划
D. 审查相关方的需求
【单选题】
CCD108、一个项目已经结束,然而项目经理和项目团队成员仍然被要求解决技术问题,进行一些小的变更,并评估新的需求,若要保证项目开发的产品现在具有运营支持,项目经理应该怎么做?___
A. 执行项目转交
B. 获得项目验收
C. 解散项目团队并找到一个新项目
D. 就像产品在开发中一样满足所有剩余需求
【单选题】
CCD109、项目经理正在制定一个关键项目的资源管理计划,该项目涉及位于不同国家具有不同文化的资源,下列哪一项将帮助项目经理处理这种情况?___
A. 团队建设活动
B. 事业环境因素
C. 人际关系技能
D. 虚拟团队
【单选题】
CCD110、对于一个新的研发项目,必须估算一些有风险活动的成本。为确保高准确性,项目经理应该使用什么估算技术?___
A. 参数估量
B. 类比估量
C. 质量成本(COQ)
D. 三点估算法
【单选题】
CCD111、产品设计被认为是各种制造问题的根本原因,若要在将来避免面对同样的问题,项目经理应该怎么做?___
A. 执行实施质量保证过程
B. 审查过程改进计划
C. 执行实施整体变更控制过程
D. 更新经验教训知识库
【单选题】
CCD112、最近发布的一项新技术可以将正在进行的项目的开发任务加快30%,团队非常渴望使用这项新技术,但识别到由于缺乏知识和支持而可能出现问题的风险。项目经理和团队如何确定使用这种技术是否会让项目收益?___
A. 审查风险管理计划,以确定新技术是否是一项不必要的风险
B. 执行定量风险分析,且如果风险排在前10位,就拒绝使用这项新技术
C. 使用挣值技术,如果挣值分析乐观就使用这项新技术
D. 执行敏感性分析以确定对项目结果可能的影响
【单选题】
CCD113、一个组织正在开始一个大型的,首个这种类型的项目,项目经理与相关方召开会议。以识别潜在的项目问题。项目经理应该使用什么工具和技术来改进会议的结果?___
A. 头脑风暴,德尔菲技术和访谈
B. 头脑风暴,因果图和流程图
C. 头脑风暴,风险分类和专家判断
D. 头脑风暴,影响图以及优势丶劣势丶机会与威胁(SWOT)分析
【单选题】
CCD114、在执行项目期间,发生了一个意外情况。项目经理应该审查哪些信息来确定适当的行动?___
A. 团队社交门户
B. 项目管理计划
C. 经验教训
D. 专家判断
【单选题】
CCD115、由于项目执行期间的范围变更,项目经理确定供应商必须对一个已在使用的产品模块进行变更,项目经理应该先做什么?___
A. 准备一份变更请求,以更新供应商的合同条款
B. 检查采购管理计划和合同条款
C. 将此信息更新到风险登记册和问题日志
D. 直接与供应商谈判达成一致
【单选题】
CCD116、一个项目需要进行一个新国家销售产品的可行性研究。项目经理应使用什么合同类型?___
A. 工科合同(TAM)
B. 总价加经济价格调整合同(FP-EPA)
C. 成本加奖励费用合同(CPAF)
D. 成本加激励费用合同(CPIF)
【单选题】
CCD117、创建项目章程的项目发起人需要已包含工作的成本估算,由于组织已经完成许多类似的项目。发起人寻求项目经理的帮助。项目经理应该使用什么来创建适合的估算?___
A. 粗略量级估算
B. 自下而上估算
C. 类比估算
D. 专家判断
【单选题】
CCD118、项目团队成员遗漏可交付成果。若要解决这个问题,项目经理首先应该做什么?___
A. 收集由团队执行的活动和相关信息
B. 将工作委托给高级团队成员,让其担任主管
C. 将所有团队成员的工作分成相等的部分
D. 提供培训,以便团队成员可以处理额外的工作
【单选题】
CCD119、在项目启动大会之后,分配给项目团队的一位技术专家对被选中参与项目工作态度很消极,为避免对其他项目成员造成负面影响。项目经理应该怎么做?___
A. 请求人力资源部门替换这位技术专家
B. 尝试去理解这位技术专家的态度,并基于收集到的信息再采取进一步行动
C. 给该技术专家发出书面警告他言行的不当,以避免对其他成员造成负面影响
D. 给该技术专家分配一项可以避免跟其他人有互动的任务
【单选题】
CCD120、一份重要项目文件的过期版本被误发给一组项目相关方。更新问题日志之后,项目经理下一步应该做什么?___
A. 确定纠正措施并执行缺陷补救。
B. 确定预防措施并执行缺陷补救。
C. 确定纠正措施并更新工作绩效报告。
D. 确定预防措施并更新工作绩效报告。
【单选题】
CCD121、一个平衡矩阵组织中的项目管理办公室(PMO)必须向CEO提供某项目状态,进度,资源统计和项目组合指标的季度报告,为完成这个目标,项目经理应该注意什么?___
A. 沟通模型
B. 项目管理信息系统
C. 会议
D. 绩效报告
【单选题】
CCD122、项目发起人希望减少质量保证时间来缩短进度,项目经理应该怎么做?___
A. 减少质量保证时间
B. 执行质量成本(coq)分析
C. 告诉发起人项目管理计划中关于质量保证(qa)的部分
D. 与质量保证团队一起进行时间估算
【单选题】
CCD123、因为所在国家的政治局势发生变化,项目经理的公司决定停止在此国发布新产品,并将产品等转卖给竞争对手,请问这是采取什么风险手段?___
【单选题】
CCD124、由于一名资源过度承诺而导致一些任务未完成。项目经理意识到如果使用其他资源将不能按时完成关键路径。项目经理应使用什么来满足进度计划?___
A. 假设情景分析
B. 资源平衡
C. 赶工
D. 资源平滑
【单选题】
CCD125、一位关键相关方威胁起诉承包商,因为一个关键功能无法按预期执行,承包商却认为他们已经按照约定履行了合同。在采购行动之前,项目经理应该查看哪份文件?___
A. 质量管理计划
B. 需求跟踪矩阵
C. 项目范围说明书
D. 验收标准
【单选题】
CCD126、制定项目章程时,销售团队和运营团队对高层次项目描述和需求意见不一致。项目经理应该怎么做?___
A. 使用专家判断来完成项目章程。
B. 安排一次与项目发起人的会议。
C. 应用引导技术解决问题。
D. 使用可用的详细信息完成项目章程。
【单选题】
CCD127、一个施工项目位于热带地区,该项目的风险登记册包括雨季洪水的风险,现在雨季已经结束,项目即将完成。应使用哪一项工具或技术来管理这个风险?___
A. 风险再评估
B. 风险转移
C. 风险规避
D. 风险审计
【单选题】
CCD128、在执行一个几乎落后于进度的项目时,项目经理必须试运行一台新设备。一个会被该项目影响的当地组织要求立即停止项目,因为没有向他们提供批准项目的机会。若要避免这个问题,项目经理应该事先做什么?___
A. 使用冲突管理技术
B. 获得所有相关方签署和批准项目章程
C. 使用谈判和影响技巧和技能
D. 实施相关方管理计划
【单选题】
CCD129、项目经理正在执行一个新的项目,以解决之前完成的一个项目的差距。项目经理首先应该做什么?___
A. 计划使用相同的项目资源
B. 准备项目管理计划
C. 定义要求,并最终确定范围
D. 参阅经验教训文件
【单选题】
CCD130、在一个高层管理会议上,定义了战略组织目标。其中一个目标是通过进入本地区内的一个细分市场提高8%的销售组合。一名项目经理被任命管理这个项目。项目经理下一步应该怎么做?___
A. 执行成本效益分析。
B. 召开焦点小组会议收集市场调研。
C. 执行相关方分析。
D. 查阅组织过程资产。