刷题
导入试题
【单选题】
The administrator wants to power on VM-K2, which has a 2GHz CPU reservation. VM-M1, VM-M2, and VM-K1 are all powered on. VM-K2 is not powered on. The exhibit shows the parent and child resource reservations. If Resource Pool RP-KID is configured with an expandable reservation, which statement is true?___
A. VM-K2 will be unable to power on because there are insufficient resources.
B. VM-K2 will be able to power on since resource pool RP-KID has 2GHz available.
C. VM-K2 will be unable to power on because only 2GHz are reserved for RP-KID.
D. VM-K2 will receive resource priority and will be able to power on this scenario.
查看试卷,进入试卷练习
微信扫一扫,开始刷题
答案
A
解析
暂无解析
相关试题
【单选题】
Which is the block size on the VMFS6 datastore?___
A. All small and large file blocks are 8MB.
B. All small and large file blocks are 1MB.
C. Small file blocks are 512KB. large file blocks are 64MB.
D. Small file blocks are 1MB, large file blocks are 512MB.
【单选题】
When installing vCenter Converter Standalone, why must an administrator perform a client-server installation instead of a local installation?___
A. to manage conversion tasks remotely
B. to convert virtual machines as well as physical machines
C. to allow installation of the Converter agent on remote source machines
D. to hot clone physical or virtual machines
【单选题】
Which is required by vCenter Converter Standalone to convert a physical Red Hat Enterprise Linux 7 machine to a virtual machine?___
A. The Linux machine must be powered off.
B. The Linux machine must have the SSH daemon started.
C. The Linux machine must use a static IP address.
D. The Linux machine must have a fully-qualified domain name.
【单选题】
An administrator is troubleshooting network communications between a vCenter Server and an ESXi 6.5 host. Which log shows the related events between these components?___
A. /var/log/fdm.log
B. /var/log/vpxa.log
C. /var/log/hostd.log
D. /var/log/auth.log
【单选题】
An administrator has recently upgraded from vSphere 6.0 to 6.5, and can no longer see the software iSCSI named vmhba33. Which could be the reason for this?___
A. The upgrade has changed the vmhba name.
B. vSphere 6.5 automates iSCSI configurations.
C. vSphere 6.5 no longer supports software iSCSI.
D. The upgrade has deleted the vmhba.
【单选题】
An administrator is trying to vMotion a VM from his datacenter to a recovery site. Which is the maximum allowed RTT (Round-Trip Time) latency between source and destination host?___
A. 100 milliseconds
B. 150 milliseconds
C. 15 milliseconds
D. 10 milliseconds
【单选题】
Which is required for configuring iSCSI Software Adapter network port binding?___
A. VMkernel of the iSCSI traffic must be load balanced using Route based on IP Hash algorithm.
B. VMkernel of the iSCSI traffic must be load balanced using Route based on Source Virtual Port ID algorithm.
C. VMkernel of the iSCSI traffic must be load balanced using Route based on Source MAC Hash algorithm.
D. VMkernel of the iSCSI traffic must be bound to only one active network adapter.
【单选题】
In vSphere Data Protection 6.1, which is the function of a Backup Verification job?___
A. None. Backup Verification job is not a feature of vSphere Data Protection
B. It is a manual task -Power it on -Verify the guest OS -Check started applications
C. It is an automatic process -Restore a virtual machine -Power it on -Verify that the guest OS is booted by communicating with the Backup Verification agent
D. It is an automatic process -Restore a virtual machine -Power it on -Verify that the guest OC is booted by detecting the VMware ToolsTM "heartbeats"
【单选题】
An administrator has enabled vSphere Distributed Switch Health Check. The hosts connected to that Distributed Switch all display an alert:< vSphere Distributed Switch MTU supported status > .The administrator has all of the VMkernel ports MTU sizes set to 1600. Which action will remedy this problem?___
A. Configure the Distributed Switch to MTU 9100.
B. Disconnect and reconnect the physical network cable.
C. Configure the physical switch to MTU 1600.
D. Disable the Distributed Switch MTU.
【单选题】
Which Host Profile Subprofile configuration is used to configure firewall settings for ESXi hosts?___
A. Advanced Configuration Settings
B. General System Settings
C. Security
D. Networking
【单选题】
Where would a vSphere administrator find general vCenter Server logs on a vCenter Server Appliance?___
A. /var/log/vmware/vpxd/
B. /var/log/messages
C. /etc/vmware-vpx/
D. /var/log/vmware/vsan-health/
【单选题】
An administrator wishes to enable network port mirroring based on source port. Which feature should be enabled?___
A. vSphere standard switch port
B. ERSPAN
C. NSX Virtual Wire
D. VLAN
【单选题】
Which CLI command shows the physical uplink status for a vmnic?___
A. esxcli network ip connection list
B. esxcli network ip neighbor list
C. esxcli network nic get
D. esxcli network nic list
【单选题】
Which is the maximum number of block devices (LUNs) that are supported by ESXi hosts that are running version 6.5?___
A. 1024
B. 512
C. 2048
D. 256
【单选题】
When performing a vCenter Server 5.5 for Windows with Microsoft SQL Server Express database migration to vCenter Server Appliance 6.5, which will be the target database?___
A. Microsoft SQL Server Express 2012R2
B. Microsoft SQL Server Standard 2012R2
C. PostgreSQL
D. Oracle DB 11g
【单选题】
An administrator has multiple vCenter Server 6.5 systems but cannot enable Storage I/O Control (SIOC) on a datastore shared by ESXi hosts managed by the vCenter Server systems. Which action should the administrator take to resolve the issue?___
A. Unmount the datastore and then enable SIOC on the vCenter Server system.
B. Configure the datastore to be managed by a single vCenter Server system.
C. Configure Storage DRS and then enable SIOC on the vCenter Server system.
D. Enable Raw Device Mapping (RDM) on the
E. SXi hosts.
【单选题】
“OneAppServer” is a VM template stored in a content library named “LibraryOne”, but the vSphere administrator is not able to use this template for deployment. Why is the administrator unable to deploy OneAppServer?___
A. OneAppServer must be updated before it can be deployed.
B. LibraryOne is a subscribed library and OneAppServer is not downloaded yet.
C. LibraryOne is published and optimized for syncing over HTTP.
D. OneAppServer was imported from a local file on the system.
【单选题】
An administrator sets the Failover Capacity for both CPU and Memory at 25%. Based on the Exhibit below, how much of the cluster’s total CPU resources are still available to power on additional virtual machines?___
A. 45%
B. 25%
C. 70%
D. 60%
【单选题】
Which statement applies to the vSphere Replication appliance?___
A. Only one vSphere Replication appliance can be deployed per vCenter Server instance.
B. VMware Tools in the vSphere Replication appliance can be upgraded.
C. A single vSphere Replication appliance can manage a maximum of 4000 replications.
D. vSphere Replication is available only with the vSphere
E. ssentials Plus license.
【单选题】
Which esxcli namespace can a vSphere Administrator use to adjust the queue depth?___
A. esxcli system module parameters
B. esxcli storage core device
C. esxcli system module set
D. esxcli storage core adapter
【单选题】
Which statement regarding datastore clusters meets VMware’s recommended best practices?___
A. Clusters should contain only datastores presented from the same storage array.
B. Clusters should contain only datastores with equal hardware acceleration capability.
C. Clusters should contain only datastores with the same capacity.
D. Clusters should contain only datastores using the same connection method (iSCSI, FC, etc.).
【单选题】
What VM Monitoring setting would ensure that the maximum reset window for a virtual machine is 24 hours?___
A. Medium
B. Low
C. High
D. Normal
【单选题】
What is the default space threshold for vSphere Storage DRS?___
A. 80%
B. 70%
C. 90%
D. 95%
【单选题】
Which is the correct sequence to upgrade a vSphere infrastructure?___
A. vCenter Server>ESXi host> VMware Tools>VM compatibility
B. ESXi host>vCenter Server> VMware Tools>VM compatibility
C. vCenter host> ESXi host> VM compatibility> VMware Tools
D. ESXi host>vCenter Server> VM compatibility>VMware Tools
【单选题】
An administrator has a large boot from SAN cluster and wants to ensure consistent configuration by using host profiles. What special considerations are required for boot from SAN hosts?___
A. Change the “Device is shared clusterwide” setting to “false” in the host profile.
B. Verify that the boot LUN is correctly identified as the boot device in the host profile.
C. The boot from SAN device must report as a local device.
D. Host profiles are incompatible with boot from SAN hosts.
【单选题】
When using VMware Converter to import a Windows server and improve the consistency of the destination virtual machine, which optional step can be performed immediately prior to powering down the source server?___
A. Perform a final synchronization task.
B. Remove the server from the network.
C. Uninstall production applications.
D. Remove the server from the Active Directory domain.
【单选题】
Restoration of the vCenter Server Appliance is accomplished using which interface?___
A. vSphere Web Client
B. vSphere Client
C. vCenter Server Appliance Management Interface
D. vCenter Server Appliance GUI Installer
【单选题】
When attempting to migrate a virtual machine to another host in the same cluster, the error message, “Select a valid compute resource” returns. What could cause this error?___
A. Both hosts run different versions of ESXi.
B. Both hosts are not sharing the same datastore.
C. VMware Tools is not installed.
D. Virtual machine has an ISO attached.
【单选题】
When will vSphere Data Protection delete the expired backup image of a Platform Service Controller?___
A. Immediately after the retention period has expired.
B. After the expired backup image is restored.
C. During the next backup window following expiry.
D. During the next maintenance window following expiry.
【单选题】
Group A has permission to download files in Content Library. Group B does not have permission to download files in Content Library. If a user is a member of both groups, what will be the result?___
A. The user cannot download file from Content Library.
B. The user can download file from Content Library.
C. The user cannot access Content Library.
D. The user can access Content Library.
【单选题】
An administrator is trying to set up Host Partial Failure Response, but the Automated option is grayed out. What can the administrator change to enable the Automated option?___
A. Change the vSphere DRS Automation level to Partially Automated.
B. Change the vSphere DRS Automation level to Fully Automated.
C. Enable vSphere HA Host Monitoring.
D. Change the vSphere DPM Automation level to Automatic.
【单选题】
When you attempt to open a virtual machine console from the vSphere Web Client, the console does not connect. The following error message appears:<HTTP ERROR 404> <Problem accessin/.Reason: Not Found>. Why did not connect?___
A. Port 443 is in use.
B. Port 9443 is in use.
C. Port 8443 is in use.
D. Port 22443 is in use.
【单选题】
What new feature was introduced to the Content Library in vSphere 6.5?___
A. Mount an ISO directly from the Content Library.
B. Deploy a virtual machine from an OVF Package in a Content Library.
C. Upload a File from a URL to a Library Item.
D. Upload a File from a Local System to a Library Item.
【单选题】
How can an administrator exclude Encryption rights from a support engineer?___
A. Clone the role Virtual machine power user, remove Cryptographic operations privileges.
B. Clone the role Administrator and assign to the support engineer.
C. Clone the role Virtual machine power user and assign to the support engineer.
D. Clone the role No cryptography administrator and select privileges only for the support engineer.
【单选题】
The administrator must back up a vCenter HA deployment. Which component must be backed up?___
A. Passive node
B. Witness node
C. External database
D. Active node
【单选题】
What is the supported protocol to perform remote L3 traffic monitoring in vSphere 6.5?___
A. VXLAN
B. ERSPAN
C. RSPAN
D. SPAN
【单选题】
What are the minimum hardware requirements for a Windows vCenter Server with embedded PSC that manages a “Small” environment?___
A. 2vCPUs, 16 GB RAM
B. 4 vCPUs, 16 GB RAM
C. 2 vCPUs, 10 GB RAM
D. 4 vCPUs, 10 GB RAM
【单选题】
Which port is used for communication between ESXi and vSphere Data protection?___
A. 80
B. 443
C. 902
D. 22
【单选题】
What can prevent Storage DRS from functioning on a datastore?___
A. The datastore is configured for Virtual Machine Swapfile location.
B. The datastore is shared across multiple datacenters.
C. The datastore is connected to a host that is running Storage I/O Control.
D. Storage DRS advanced option IgnoreAffinityRulesForMaintenance is set to 1.
【单选题】
When troubleshooting VMware vCenter Server issues, when logging level provides maximum detail?___
A. Verbose
B. Trivia
C. Info
D. Error
推荐试题
【单选题】
"《关于加强铁路建设项目保证金管理的通知》的规定,铁路项目收取的保证金主要有投标保证金、履约保证金和质量保证金三种,其中投标保证金的额度不得超过最高投标限价的___,且不超过80万元。
A. 1.5%
B. 2%
C. 3%
D. 5%"
【单选题】
"《关于转发财政部、税务总局调整增值税税率等5个文件的通知》的规定,自___起,各单位从事销售货物、提供加工修理修配劳务和有形动产租赁服务等业务,适应税率由17%调整为16%;从事提供交通运输、建筑、不动产租赁服务等业务,适应税率由11%调整为10%。
A. 2017年5月1日
B. 2017年6月1日
C. 2018年5月1日
D. 2018年6月1日"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文的规定,项目初步设计批复总概算超出批复投资估算的,报请总公司建设项目技术投资协调小组研究决策,其中项目初步设计总概算增加超出批复投资估算___时,需按原可行性研究审批程序办理调整可研后批准执行。
A. 3%
B. 5%
C. 8%
D. 10%"
【单选题】
"根据《铁路基本建设项目投资管理办法》的规定,铁路项目___及以后的新开工项目在建成收尾消号前,建设单位在初步设计批复概算内,根据实施推进情况,对项目实际发生费用进行清理,清理结果报计划统计部、工程管理中心、工程设计鉴定中心核备。
A. 2012年
B. 2014年
C. 2016年
D. 2017年"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文的规定,在项目实施过程中,因勘察设计达不到规定深度或质量原因引起变更设计,设计单位承担无偿设计责任,累计投资变化超过静态投资___的,可按照超过投资的2%扣减设计费。
A. 2%
B. 3%
C. 5%
D. 10%"
【单选题】
"《 关于印发建设工程质量保证金管理办法的通知》建质[2017]138号文的规定,缺陷责任期从工程通过竣工验收之日起计,由发包人原因导致工程无法按规定期限进行竣工验收的,在承包人提交竣工验收报告___天后,工程自动进入缺陷责任期。
A. 14
B. 28
C. 90
D. 120"
【单选题】
"《公路工程营业税改征增值税计价依据调整》规定,自___起,执行《公路工程基本建设项目投资估算编制办法》等公路工程计价依据。
A. 2015年5月1日
B. 2016年5月1日
C. 2017年5月1日
D. 2018年5月1日"
【单选题】
"依据《铁路征地拆迁及费用管理的指导意见》铁总计统[2017]177号文的规定,征地拆迁工作坚持依法合规和维护被征拆人合法权益,执行国家和省级人民政府颁布的有关规定和标准,对于特殊情况下突破政策和规范要求,单项拆迁额___以上的重大补偿事项必须由建设单位上报总公司管理中心核备后执行。
A. 300万元
B. 500万元
C. 1000万元
D. 2000万元"
【单选题】
"依据《铁路征地拆迁及费用管理的指导意见》铁总计统[2017]177号文的规定,初步设计阶段的征地拆迁数量、补偿标准、费用要与可行性研究阶段逐一进行对照分析,增减幅度超出___的,应要求设计单位书面说明缘由。
A. 2%
B. 3%
C. 5%
D. 10%"
【单选题】
"根据《关于印发铁路工程混凝土结构高强钢筋设计规定》铁总建设[2015]343号文 的规定,自___后施工的铁路工程,由建设单位组织设计单位等参建单位,对混凝土结构设计图进行梳理,按《铁路工程混凝土结构高强钢筋设计规定》的通知要求检算,凡具有优化设计条件的,应修改施工图纸。
A. 2015年3月1日
B. 2016年3月1日
C. 2015年5月1日
D. 2016年5月1日"
【单选题】
"《铁建设项目“四电”工程招标管理有关事项》铁总建设[2016]152号文 的通知,高速铁路和时速___公里客货共线铁路,潜在投标人须具备铁路电务、电气化专业承包一级资质。
A. 100
B. 160
C. 200
D. 300"
【单选题】
"依据《 关于安全生产费提取和使用管理办法》铁建设【2012】245号文规定,安全生产费使用范围包括___大类53小项内容。
A. 5
B. 7
C. 9
D. 10
【单选题】
"《关于发布长钢轨供应有关费用标准的通知》铁建设[2012]2号文的规定,长钢轨供应有关费用是特指在合理的施工组织和正常的施工条件下,单根长度___米及以上钢轨从焊轨基地供应到铺轨基地所发生的部分费用。
A. 50
B. 100
C. 150
D. 200"
【单选题】
"依据《 关于印发建设工程质量保证金管理办法的通知》建质[2017]138号文规定,发包人在接到承包人返还保证金申请后,应于___天内会同承包人按照合同约定的内容进行核实,如无异议,发包人应当按照约定将保证金返还给承包人。
A. 7
B. 14
C. 28
D. 30"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文的规定,铁路项目招标人要合理确定工程招标最高投标限价,最高投标限价同比不得超过标段___。
A. 投资估算
B. 初步设计概算
C. 施工图预算
D. 可研批复概算"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文的规定,铁路项目的实施阶段设计、施工图审核单位进一步对工程措施优化,建设单位可按优化节省投资的___增加提出单位的相关费用。
A. 1%-3%
B. 3%-5%
C. 5%-10%
D. 10%-15%"
【单选题】
"《铁路建设项目施工现场设计配合管理办法》铁总建设[2017]175号文的规定,设计单位根据现场变化及时完善勘察设计工作,提出征地拆迁、管线迁改、交叉跨越、市政配套接口等设计方案,协助___完善相关协议。
A. 监理单位
B. 建设单位
C. 施工单位
D. 地方政府单位"
【单选题】
"按《营改增后铁路基本建设工程相关造价标准调整》铁总建设[2016]359号文 规定,建筑业自___起纳入营业税改征增值税试点范围。
A. 2015年5月1日
B. 2016年5月1日
C. 2015年7月1日
D. 2016年7月1日"
【单选题】
"按《关于铁路建设项目实施阶段材料价差调整的指导意见》铁建设【2009】46号文规定,铁路项目施工企业自购料价差计算的材料数量为___。
A. 采购数量
B. 投标概算数量
C. 设计概算数量
D. 投资估算数量"
【单选题】
"根据铁路工程项目常规合同约定,下列不属于总承包风险费的是___。
A. 考核费用
B. 限额以下的II类变更设计
C. 变更施工方法所引起的费用增加
D. 新增工程"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文 的规定,铁路项目概算清理费用主要由___两部分组成。
A. I类变更设计和II类变更设计
B. 已批复概算和清理概算增加投资
C. 征地拆迁和变更设计
D. 政策性收费和施工图量差"
【单选题】
"根据《关于印发铁路工程混凝土结构高强钢筋设计规定》铁总建设[2015]343号文 的规定,凡因执行本规定要求需变更设计的,由___组织并按规定程序办理。
A. 建设单位
B. 勘察设计单位
C. 施工单位
D. 监理单位"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文的规定,地方政府为方便民众出行而提出增设非等级道路跨线设施,由建设单位按照尽量节省投资的原则与地方政府协商设置规模和原则,按___办理。
A. 新增变更设计
B. II类变更设计
C. I类变更设计
D. 总承包风险费"
【单选题】
"《关于转发财政部、税务总局调整增值税税率等5个文件的通知》铁总办财[2018]58号文要求,铁路基本建设工程设计概预算建筑安装工程费税金与设备购置税金税率按___计列,2018年5月1日前初步设计已批复的项目设计概算不再调整。
A. 3%
B. 10%
C. 11%
D. 16%"
【单选题】
"《关于规范铁路营业线施工配合技术服务费计取工作的指导意见》铁总建设[2017]146号文规定,邻近营业线施工范围,一般情况下指铁路线路路堤坡脚、路堑坡顶、铁路桥梁外缘、铁路隧道上方中心线的两侧向外各___米范围内的爆破工程。
A. 20
B. 100
C. 500
D. 1000"
【单选题】
"《关于规范铁路营业线施工配合技术服务费计取工作的指导意见》铁总建设[2017]146号文规定,铁路工程施工阶段,根据铁路营业线施工安全管理相关规定和工程现场实际情况,确需对一般情况下的施工配合技术服务范围进行调整或施工组织方案发生重大变化时,___应组织相关单位对技术服务费进行论证,增减的费用按变更设计程序处理,在预备费用中列支。
A. 铁路局
B. 建设单位
C. 运营单位
D. 勘察设计单位"
【单选题】
"根据《铁路基本建设项目投资管理办法》铁总计统[2017]179号文的规定,铁路项目建设过程中,建设管理、勘察设计单位对变更设计严格把关,控制变更设计费用。对建设单位审批变更设计费用超出可使用___的项目,按照建设单位考核职责分工,由工程设计鉴定中心提出考核意见,纳入建设单位考核。
A. 降造费
B. 预备费
C. 投标节约
D. 施工图预算与初步设计概算差额"
【单选题】
"《铁路征地拆迁及费用管理的指导意见》铁总计统[2017]177号文 规定,根据铁路项目征拆实施协议约定,由地方政府组织征地拆迁工作,在施工队伍进场前提交___以上的红线用地,或与产权单位签订80%以上补偿协议,全部征地拆迁工作在6-8月内完成,没有达到上述要求时建设单位不得组织施工单位进场开展施工。
A. 30%
B. 50%
C. 60%
D. 80%"
【单选题】
"《关于铁路建设验工计价办法的通知》铁总建设[2014]298号文规定,季度验工计价应在次季度首月___日前完成,节点验工计价应在工程总承包单位提出申请后十日内完成,末次验工计价应在初验后、正式验工前完成。
A. 7
B. 10
C. 14
D. 28"
【单选题】
"住房城乡建设部、交通运输部、水利部、人力资源社会保障部四部委于___共同发布了《关于印发<造价工程师职业资格制度规定><造价工程师职业资格考试实施办法>的通知》。
A. 2018年3月12日
B. 2018年4月12日
C. 2017年4月12日
D. 2018年7月20日 "
【单选题】
"具有工程管理、工程造价专业大学本科及以上学历或学位,从事工程造价业务工作满___,可以申请参加二级造价工程师职业资格考试。
A. 1年
B. 2年
C. 3年
D. 4年"
【单选题】
"具有通过工程教育专业评估(认证)的工程管理、工程造价专业大学本科学历或学位,从事工程造价业务工作满___可以申请参加一级造价工程师职业资格考试。
A. 2年
B. 3年
C. 4年
D. 5年
【单选题】
"具有工程造价专业大学专科(或高等职业教育)学历,从事工程造价业务工作满___,可以申请参加一级造价工程师职业资格考试。
A. 2年
B. 3年
C. 4年
D. 5年
【单选题】
___负责审定一级造价工程师和二级造价工程师职业资格考试科目和考试大纲。
A. 交通运输部
B. 房城乡建设部
C. 人力资源社会保障部
D. 地方造价管理站
【单选题】
一级造价工程师英文译为___。
A. “Senior Engineer”
B. “First Class Engineer”
C. “Class1 Cost Engineer”
D. “Primary Cost
E. ngineer”
【单选题】
二级造价工程师职业资格考试设《建设工程造价管理基础知识》和___2个科目。
A. 《建设工程计价》
B. 《建设工程技术与计量》
C. 《建设工程计量与计价实务》
D. 《建设工程造价案例分析》
【单选题】
一级造价工程师职业资格考试成绩实行___年为一个周期的滚动管理办法,在连续的___个考试年度内通过全部考试科目,方可取得一级造价工程师职业资格证书。___
A. 2,2
B. 3,3
C. 4,4
D. 1.1
【单选题】
二级造价工程师职业资格考试成绩实行___年为一个周期的滚动管理办法,参加全部2个科目考试的人员必须在连续的___ 个考试年度内通过全部科目,方可取得二级造价工程师职业资格证书。
A. 2,2
B. 3,3
C. 4,4
D. 1.1
【单选题】
建筑安装工程费按照费用构成要素划分:由人工费、材料(包含工程设备)费、施工机具使用费、___、利润、规费和税金组成。
A. 措施项目费
B. 其他项目费
C. 社会保险费
D. 企业管理费
【单选题】
下列选项中,不属于施工机械使用费组成部分的是___。
A. 安拆费及场外运费
B. 人工费
C. 工地转移费
D. 企业管理费
欢迎使用我爱刷题
×